August 012018

UPDATE: Upcoming Traffic & Pedestrian Changes at Eglinton Station

What Work is Taking Place?

Support of excavation work, also known as shoring, has commenced to make way for the future Eglinton interchange station. This work will include pile installation, jet grouting and road deck installation. Shoring at the TTC bus depot and along south side of Eglinton has been complete. The work is carried out along the north side of Eglinton.

The next phase (depicted below) will take approximately 2-3 months to complete. The entire shoring process will take approximately twenty-four (24) months to complete. Read more »

August 012018

Construction Notice - Leaside Station - Traffic Flip

UPDATE: TRAFFIC & PEDESTRIAN CHANGES

LEASIDE STATION

 

In early August, the traffic conditions at Bayview Avenue and Eglinton Avenue East will change. There will be lane reductions on Bayview Avenue as well as new turn restrictions at the intersection. Read more »

July 262018

Upcoming Works at Eglinton Station: Subsurface Utility Engineering (SUE) Investigations

What Work is Taking Place?

To prepare for upcoming shoring activities, crews will be conducting Subsurface Utility Engineering (SUE) investigations along the right-of-way on the south side of Eglinton Avenue from Cowbell Lane to Holly Street. Pedestrian access along Eglinton Avenue East from Cowbell Lane to Holly Street will be maintained.

Crews will drill bore holes and use a hydro-vacuum truck within the public right-of-way to determine the location of the underground utilities and the ground conditions around the intersection for design purposes.  Read more »

July 232018

UPDATE: Additional Monitoring Wells at Avenue Station

WHAT WORK IS TAKING PLACE?

Two additional monitoring wells are required at the Avenue Station, east of the Secondary Entrance. These wells  support the ongoing monitoring instruments installations required at Avenue Station. Read more »

July 202018

Upcoming Traffic Changes at Kennedy and Eglinton In Support of Shoring

What Work is Taking Place?

As part of the continued support of excavation works (shoring) and utility relocations for the future Kennedy Station, traffic staging at the intersection of Kennedy Road and Eglinton Avenue East will be changing in late July. Shoring began in April 2018 and will continue in phases at the intersection, taking approximately twelve (12) months to complete. Read more »

July 202018

Construction Notice - Leaside Station - Overnight Line Painting

Overnight Line Re-Painting at Leaside Station

 

WHAT WORK IS TAKING PLACE?

Leaside station crews will complete a refresh of some of the crosswalks and lines in around the Bayview Ave and Eglinton Ave E intersection. Due to the volumes of traffic in the area and existing construction set up reducing available lanes, these works will be completed overnight. Read more »