October 042017
October 022017

Update: Mining at Laird Station Main Entrance

Original Issue Date: September 19, 2017

Re-issue Dates: October 2, 2017  Read more »

October 022017

Elevated Guideway Piling

 

Elevated Guideway & West Portal Read more »

September 292017

Update: Shoring and Excavation at Oakwood Station

 

Original Issue Date: July 12, 2017

Re-issue Dates: September 4 and 29, 2017 Read more »

September 292017

Traffic Change at Fairbank Station - September 2017

Notice originally posted on September 15, 2017.

What Work is Taking Place? Read more »

September 292017

UPDATE: Toronto Hydro-Electric System Development for Eglinton Station

What Work is Taking Place

Notice originally posted on June 7, 2017 - Updated on September 29, 2017

Update: Crews completed a majority of the hydro relocation work over the summer, and will be completing the work along Hillsdale Avenue and Yonge Street over the coming months.  The laydown area on Berwick Avenue has been extended to January 31, 2018. Read more »

September 292017

Cedarvale Station: Overnight Crosswalk Line Painting & Road Decking Inspection - Oct 1 & Oct 2

What Work is Taking Place?

  • Two nights of overnight work on Eglinton Avenue West at Allen Road are required.
  • Work will be done overnight while traffic volumes are low.
  • Minimal noise is expected from both pieces of work.
  • Work may be delayed due to weather conditions or unforeseen circumstances.

 

Crosswalk Line Painting

MIDNIGHT on SUNDAY, OCTOBER 1 until APPROXIMATELY 2AM on MONDAY, OCTOBER 2 Read more »