February 262016

Demolition Work for Future Mount Pleasant Station

What work is starting?

In February 2016, crews began conducting preparatory activities and utilities works including surveying, locating utilities, and drilling boreholes to obtain additional information of sub-surface utilities and ground conditions in the Mount Pleasant Road and Eglinton Avenue East vicinity to make way for the future Mount Pleasant Station.

Upcoming Works – Demolition Read more »

February 262016

Geotechnical Testing for Future Eglinton Station

What work is starting?

In February 2016, crews began conducting preparatory activities in the Yonge Street and Eglinton Avenue West vicinity to make way for the future Eglinton Station.

Upcoming Works – Geotechnical Testing   Read more »

February 242016

Demolition Work at Future Avenue Station

Upcoming Work – Demolition and Selective Street Furniture Removal Read more »

February 242016

Demolition Work for Future Laird Station

What work is starting?

In February 2016, crews began conducting preparatory activities and utilities works including surveying, locating utilities, and drilling boreholes to obtain additional information of sub-surface utilities and ground conditions in the Laird Avenue and Eglinton Avenue East vicinity to make way for the future Laird Station.

Upcoming Works – Demolition Read more »

February 242016

Temporary Closure of Holly Street at Eglinton Avenue East

What we are building

What: Holly Street will be temporarily closed, due to continued work on the construction of the extraction shaft located on the south side of Eglinton Avenue East, east of Yonge Street. This work will involve daylighting and relocating utilities. Depending on site conditions, gas, hydro, water mains, sewers, traffic and street lighting, as well as telephone lines, will be relocated to allow for heavy civil construction.   Read more »

February 242016

Demolition Work for Future Eglinton Station

What work is starting?

In February 2016, crews began conducting preparatory activities in the Yonge Street and Eglinton Avenue West vicinity to make way for the future Eglinton Station.

Upcoming Works – Demolition Read more »

February 122016

Next Stage: Bayview Headwall Construction – Shift to South Side and Middle Lanes on Eglinton Avenue East

What work is starting?

What: Crews will continue constructing the east and west headwalls for the future Bayview Station in advance of the tunnelling works.  On the east side of Bayview Avenue, crews will be shifting construction to the middle lanes on Eglinton Avenue East. On the west side of Bayview Avenue, crews will be shifting construction to the south side of Eglinton Avenue East. Read more »

February 122016

Demolition Work for Forest Hill (formerly Bathurst) Station

In February 2016, crews began conducting preparatory activities in the Bathurst Street and Eglinton Avenue West vicinity to make way for the future Forest Hill Station. Read more »