February 122015

Monitoring Equipment Installation Work near Yonge Street: Temporary Closure of Southbound Holly Street from Eglinton

What we are building

What: Crews will be installing monitoring equipment on the west side of Holly Street, just south of Eglinton Avenue. This work is required prior to building support headwalls and an extraction shaft within the Eglinton Avenue roadway on the east side of Yonge Street, and is in addition to the current construction activities on the north side of Eglinton Avenue.   Read more »

February 102015

UPDATE: Bathurst Station Headwall Construction for Twin Tunnels

What we are building

What: Crews will be building headwalls for the future underground Bathurst Station. Headwalls are underground support walls located at the east and west ends of the station. Following the site preparation, crews will be installing these headwalls in advance of the twin tunnel construction. Read more »

February 062015

Tree Removal and Protection in the vicinity of 440 Eglinton Avenue East

What work is starting?

What: Crews will be removing a tree, which is adjacent to Eglinton Avenue East in the vicinity of 440 Eglinton Avenue East. Read more »

February 042015

Update: Laird West Headwall Construction on North side of Eglinton

What phase of work is starting in the vicinity of Sutherland Drive? Read more »

February 042015

Gas Line Relocation for Eglinton Crosstown LRT – Don Mills Station Starting the Week of February 2, 2015

What work is starting?

What: Enbridge Gas Distribution will be relocating natural gas pipelines for the construction of the Eglinton Crosstown tunnel and future Don Mills Station. Read more »

January 162015

Extraction Shaft Construction Work East of Yonge Street Shifting to North Side of Eglinton Avenue

What: Crews will be working on the construction of a large shaft including the building of support piles and a headwall, located within the Eglinton Avenue roadway on the east side of Yonge Street. 

Why: Crews are currently relocating utilities on the south side of Eglinton. During the next stage, construction of a large shaft will begin on the north side of Eglinton. Construction of this shaft will include daylighting for utilities, installation of piles, jet-grouting and excavation and decking of the roadway.   Read more »

January 132015

Emergency Exit Building Construction Hydro Utility Pole Relocation on Petman Avenue

What work is starting?

What: Petman Avenue hydro utility pole relocation work is necessary in advance of the construction of Emergency Exit Building.  Certain hydro utility poles located on the east side of Petman Avenue and on City of Toronto property, will be relocated to a nearby location - also on City of Toronto property. Read more »

January 082015

2014 Year-in-Review

The Eglinton Crosstown is a 19-kilometre light rail transit (LRT) line that will run along Eglinton Avenue through the heart of Toronto, with a 10-kilmetre underground tunnel in its central section. When it’s complete, the line will connect Mount Dennis in the west to Kennedy Road in the east, and will be up to 60% faster than bus service today. Read more »

January 082015

Avenue Station Headwall Construction for Twin Tunnels

What we are building?

What: In this phase of construction, crews will be building the headwalls for the future Avenue Station. Headwalls are underground support walls located at the east and west ends of the station location. Following the site preparation, crews will be installing these underground station headwalls in advance of the twin tunnel construction. Read more »