Construction Updates

Looking for information related to a specific area?

Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).

Syndicate content
 
April 122018

REISSUE: LOW WATER PRESSURE NOTICE: Watermain Connection Work for Science Centre Station

What Work is Taking Place?

Crews are working to replace an existing watermain north of Eglinton Avenue East within the existing work zone at the northeast corner of Don Mills Road and Eglinton Avenue East. This work supports the upgrade of existing water infrastructure around the future Science Centre Station. Read more »

April 122018

Sheet Piling Work at the Brentcliffe Portal

What Work is Taking Place?

Crews will be driving sheet piles as part of the Support of Excavation at the Brentcliffe Portal at the eastern end of the existing work zone, beginning as early as April 17, 2018.  Read more »

April 112018

Lane Impacts Leaside Station

WHAT WORK IS TAKING PLACE?

Work requiring the temporary closure of the southbound lane, just south of Eglinton Avenue East will occur over the next week. Southbound traffic will be maintained by removing the northbound dedicated left turn lane. 

 

TIMING 

  Read more »

April 112018

Upcoming Works: Demolition at 795 Warden Avenue

What Work is Taking Place?

Beginning as early as April 11, 2018, the property at 795 Warden Avenue will be demolished to make way for the construction of one of the Traction Power Substations (TPSS) that will power the Eglinton Crosstown Light Rail Transit (ECLRT).  The work will take place within a protected work zone. Both traffic and pedestrian pathways will not be affected by this work. Read more »

April 092018
April 072018

Overnight Utility Relocation on Transway Crescent and Kennedy Road in Support of Construction of the Future Kennedy Station

What Work is Taking Place?

As part of construction of the future Kennedy Station, crews will be relocating watermain and sanitary utilities on Transway Crescent, including a partial crossing of Kennedy Road, starting as soon as April 9, 2018. To reduce impacts to the community and commuters this work will be performed overnight and will take approximately two weeks to complete.  The work is part of the larger upgrade and relocation of utilities for the Eglinton Crosstown LRT. Read more »

April 062018

Pedestrian Route Changes Leaside Station

WHAT WORK IS TAKING PLACE?

Over the next month, crews will complete right of way works including restoration of curbs and sidewalks on the south side of Eglinton Avenue both east and west of Bayview Avenue. This will result in some periodic changes to pedestrian circulation. Please watch for orange and black signage that directs pedestrians.

These works are required to support the completion of decking and restoration of the work zone to allow crews to shift to working on the north side of Eglinton Avenue in May 2018.

  Read more »

April 052018

Upcoming Works at Eglinton Station: Temporary Manhole Construction

What Work is Taking Place?

Construction of a temporary manhole at Eglinton Avenue West and Duplex Avenue is required to enable the continued relocation of utilities for the construction of Eglinton Station.

 

Hours of Work Read more »

April 052018

Upcoming Parking Reduction at Kennedy Station in April 2018

As part of construction of the future Eglinton Crosstown Light Rail Transit (ECLRT), improvements are also being made to the GO Corridor Stouffville Line at Kennedy Station. These include building a new west platform, rebuilding the existing east platform, constructing a new ticketing building for the GO Station, and building a new south pedestrian underpass. 

In order to facilitate these improvements, roughly 113 parking spaces at the South Parking Lot will be removed so that the work can be undertaken in a safe manner. Read more »