November 282018
November 272018

Overnight Invert Concrete Pour at Kennedy Station

What Work is Taking Place?

As part of continued support for the future Kennedy Station portal construction, crews will be delivering and pouring cement along Eglinton Avenue East between Ionview Road and Kennedy Road on Thursday, November 29, 2018 from 10:00 p.m. until completion. To facilitate this delivery, concrete trucks will be arriving to the site west of Ionview Road.   

Read more »

November 262018

Updated Pedestrian Routes at Wynford Drive Bridge

What Work is Taking Place?

As part of utility relocation and bridge rehabilitation works, new traffic staging was implemented between the Don Valley Parkway off-ramps and Wynford Drive early November, 2018.

An update to pedestrian routes will take effect as early as Wednesday, November 28th, 2018. The north-south crossing that was temporarily installed at Wynford Drive will be removed. The nearest pedestrian crossing will be located at the Don Valley Parkway North ramp.  Read more »

November 232018

Construction Notice - Mount Pleasant Station - Overnight Work

Overnight Wet Utilities Work at Mount Pleasant Station

Week of November 26, 2018

 

What Work is Taking Place? Read more »

November 232018

808/817 Mount Pleasant Rd Water Shut-Off - Construction notice

NOTICE OF PLANNED OVERNIGHT WATER SHUT-OFF

MONDAY NOVEMBER 26, 2018

 

What Work is Taking Place? Read more »

November 232018

Construction Notice - Laird Station - Concrete Pours

UPDATE: New Mining Activities at Laird Station

 

WHAT WORK IS TAKING PLACE?

As work progresses underground, final lining works will begin on sections of the caverns where mining excavation is complete. Read more »

November 232018

November 27th - Overnight Water Shut-Off - Mount Pleasant

NOTICE OF PLANNED OVERNIGHT WATER SHUT-OFF

TUESDAY NOVEMBER 27, 2018

 

What Work is Taking Place? Read more »

November 232018

Construction Notice - Mount Pleasant Station - Overnight Work

Overnight Wet Utilities Work at Mount Pleasant Station

Week of November 26, 2018

 

What Work is Taking Place? Read more »

November 222018

Pre-cast Concrete Installation for Facility Services Building Construction at Eglinton Station

Beginning as early as October 26, 2018, crews will install pre-cast concrete for the Facility Services Building for the TTC Line 1 Subway system. Crews will also undertake various activities inside the TTC station. Read more »