November 072017

Traffic Changes at Leaside Station

What Work is Taking Place?

Starting as soon as Thursday, November 9th, there will be a couple of changes to the existing traffic set up around Eglinton Avenue and Bayview Avenue:

Left turn restriction from Mann Avenue to westbound Eglinton Avenue East Read more »

November 062017

Installation of Temporary Traffic Signals Across Eglinton Avenue East Between Leslie Street and Kennedy Road

Updated: November 6, 2017

Original Post: October 20, 2017

What Work is Taking Place?

Crews will remove existing traffic signals and install temporary traffic signals on Eglinton Avenue East between Leslie Street and Kennedy Road, to make way for the construction of future surface stops for the Eglinton Crosstown LRT.

Timing Read more »

November 032017

Sanitary Sewer Installation and Overnight Diversion Work at Chaplin Station

WHAT WORK IS TAKING PLACE?

Part of the work to be done within the north side work zone includes the installation of a new sanitary sewer system. The new sanitary sewer will run along Eglinton Avenue West between Chaplin Crescent and Latimer Avenue.  

To complete the installation of the new sewer, crews will need to divert the existing sanitary sewer system flow. Diversion work involves cutting into the existing sanitary sewer pipe and temporarily diverting the flow of sewage while the new pipes and property connections are installed. Read more »

November 032017
November 032017

Utilities Works at Leaside Station

What Work is Taking Place?

On Monday November 6th, work will be completed to bring power to the secondary entrance area. A small work zone will be in place on the west side of Bayview Avenue near the driveway access to the Metro Parking.

Minor utility works occur periodically within the current construction zones with no additional traffic or pedestrian impacts. Read more »

November 032017

Update: Deep Excavation and Dewatering at Caledonia Station

What work is taking place?

Deep excavation and dewatering have been underway at Caledonia Station since spring 2017. Read more »

November 022017

Overnight Watermain Works on Eglinton Avenue at Allen Road for Cedarvale Station

WHAT WORK IS TAKING PLACE?

  • In preparation for the next phase of shoring works at Cedarvale Station, crews need to cap and remove an old watermain that runs under the current Eglinton Avenue westbound lane.
  • Crews will be occupying a lane on Eglinton Avenue West from Park Hill Road to Allen Road North (in front of the TTC station) to accommodate this work.

TIMING Read more »

November 012017

Changes to the Driveways at 2360 Eglinton Avenue East: Stage 1

In Support of Upgrades to Water Infrastructure for the Eastern End of the Eglinton Crosstown LRT Line

Beginning as early as Monday, November 6, 2017 for approximately four (4) weeks, driveways at 2360 Eglinton Avenue East will be modified to support construction of the Crosstown LRT. Work will be done in two stages, each stage lasting approximately two (2) weeks.

Please see image below showing changes to access to 2360 Eglinton Avenue East during Stage 1 of this work.

What Work is Taking Place? Read more »

October 302017

Toronto Hydro-Electric System Limited (THESL) and Telecommunication Relocations (Brentcliffe to Leslie)

What Work is Taking Place?

Crews will relocate and upgrade existing overhead and underground telecommunication and hydro utilities between Brentcliffe Road and Leslie Street along Eglinton Ave East in preparation for construction of the Brentcliffe Portal and Sunnybrook Park Stop. Read more »