Construction Updates

Looking for information related to a specific area?

Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).

Syndicate content
 
October 062017

Overnight and Early Morning Works at Cedarvale Station for Roof Slab Concrete Pour and Traffic Deck Coating

What Work is Taking Place?

 

  • Next week, two nights of overnight work are required and one early morning concrete pour is planned.
  • Minimal noise is expected from both pieces of work.
  • Work may be delayed due to weather conditions or unforeseen circumstances.

 

Traffic Deck Coating

TUESDAY OCTOBER 10 at 7PM – WEDNESDAY OCTOBER 11 at 5AM

WEDNESDAY OCTOBER 11 at 7PM – THURSDAY OCTOBER 12 at 5AM

  Read more »

October 062017

Overnight Work and Lane Reductions to Install Centre Line Dewatering Wells on Eglinton for Avenue Station

Updated: October 6, 2017
Original Post: October 3, 2017

New Start Date: October 16, 2017 

 

What Work is Taking Place?

The term “dewatering” means pumping water from the ground at a site where there will be excavation and is essential before and during upcoming mining operations at Avenue Station. The dewatering system is installed in two phases, drilling of the wells and then digging shallow trenches to connect the wells and lay the pipes, pumps, and valves for the system. Read more »

October 062017

Closure of Taunton Road for Storm Sewer Installation at Mount Pleasant Station

What Work is Taking Place?

Since spring 2017, crews have been performing support of excavation (shoring) in the vicinity of Mount Pleasant Road and Eglinton Avenue East.  Shoring of the station box, located in the roadway, is currently underway on the north side of Eglinton Avenue East.  In preparation of shoring on the south side of the station box, crews will install new storm sewer infrastructure. Read more »

October 052017

Mount Dennis Station: Watermain & Fire Hydrant Connections

 

What Work is Taking Place?

As part of continued construction of the Mount Dennis Station crews will be working within the centre lane of Eglinton Avenue West from Weston Road to Black Creek Drive to complete watermain and fire hydrant connections.

This work will occur overnight beginning October 9, 2017 between the hours of 7:00 p.m. and 6:00 a.m. and is expected to take approximately two (2) weeks. Read more »

October 052017

Tunnel Backfilling Brentcliffe Road to Laird Drive

What Work is Taking Place?

To support the ongoing mining works at the future Laird Station, a layer of backfill (granular material) will be added to the base of the existing tunnel from the Brentcliffe Portal to Laird Drive. 

Backfill material will be stockpiled and then be pushed in to the tunnel at Brentcliffe Portal and inside the tunnels towards Laird Drive. Compaction of the material will occur inside of the tunnels. Read more »

October 042017
October 042017

Geotechnical Equipment Installations and Monitoring on Thursfield Crescent for the Brentcliffe Portal and Surface Stops

What Work is Taking Place?

As part of the ongoing construction works for the future Brentcliffe Portal and Surface Stops, above ground and in-ground monitoring points will be installed on the City Right-of-Way, which may include the roadway, sidewalks and/or driveways on Thursfield Crescent.

Once installed, the instruments will remain at these locations for the length of the project. Monitoring allows crews to evaluate the impact of construction works. Read more »

October 022017

Update: Mining at Laird Station Main Entrance

Original Issue Date: September 19, 2017

Re-issue Dates: October 2, 2017  Read more »

September 292017

UPDATE: Toronto Hydro-Electric System Development for Eglinton Station

What Work is Taking Place

Notice originally posted on June 7, 2017 - Updated on September 29, 2017

Update: Crews completed a majority of the hydro relocation work over the summer, and will be completing the work along Hillsdale Avenue and Yonge Street over the coming months.  The laydown area on Berwick Avenue has been extended to January 31, 2018. Read more »