March 052019

Overnight Lane Reductions for Wet Utility Works at Fairbank Station March 2019

What Work is Taking Place?

Beginning in early March 2019, crews will implement overnight lane reductions at the intersection of Dufferin Street and Eglinton Avenue West to perform sewer relocation and water discharge works.  Work will begin on Eglinton Ave approximately 40 meters east of Dufferin St, followed by Dufferin St approximately 30 meters south of Eglinton Ave, for a total of approximately five (5) nights (weather permitting).  Read more »

March 052019

Overnight Lane Reductions at Forest Hill Station March 2019

What Work is Taking Place?

Starting March 11, 2019, overnight lane reductions will resume at intersection of Bathurst Street and Eglinton Avenue West while crews perform works at Forest Hill Station.  Activities will include, installation of hydro utility infrastructure and drilling of boreholes in various locations throughout the intersection.  Read more »

March 042019

Temporary Crosswalk Removal at Fairbank Station March 2019

What Work is Taking Place?

The east crosswalk at Dufferin Street and Eglinton Avenue West will be temporarily unavailable for approximately two (2) weeks while crews perform overnight wet utility work in the intersection.  During this time, the west crosswalk will remain open.  Upon completion of the utility works, the east crosswalk will be restored.

Hours of Work

  • March 1, 2019 for approximately two (2) weeks

Construction Staging Read more »

March 042019

Guideway Work along Surface Section of the Eglinton Crosstown LRT: Warden Avenue to Birchmount Road

What Work is Taking Place?

As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will be continuing guideway work in the centre of Eglinton Avenue East between Warden Avenue and Birchmount Road. Starting as early as mid-March 2019 for approximately eight (8) months.

The work includes cutting and removal of existing asphalt, excavation, installation of subgrade materials, duct banks installation and track drainage, track slab and stops.

Stage 2 Read more »

March 042019

New Traffic Configuration: Eglinton Avenue East at Jonesville Crescent

WHAT WORK IS TAKING PLACE?

As utility installations progress along Eglinton Avenue East between Bermondsey Road and Victoria Park Avenue, four (4) new traffic stages will be implemented at Jonesville Crescent to accommodate the work zones (depicted below). Traffic will shift to the first stage as early as Monday, March 4th, 2019. Each stage will last approximately one (1) week. Read more »

March 012019

Overnight Lane Closures on Yonge Street for Toronto Hydro Infrastructure Access

What Work is Taking Place?

Crews need to access a cable chamber on the southbound lane of Yonge Street as part of Toronto Hydro utility relocation works. In order to safely carry out the work, the southbound lane on Yonge Street will be closed while crews are accessing the chamber.

 

Hours of Work Read more »

March 012019

Tower Crane Installation at Science Centre Station

Tower Crane Installation at Science Centre Station

WHAT WORK IS TAKING PLACE? Read more »

February 282019

Short Duration Water Shut Off - Avenue Station

Short Duration Water Shut Off

Sunday March 3rd, 10:00 p.m. to 6:00 a.m.

 

WHAT WORK IS TAKING PLACE?

 

Crews at Avenue Station will complete minor works on a local water main from approximately 10:00 p.m. on Sunday March 3rd to 6:00 a.m. on Monday March 4th.  

 

During the works, there will be a temporary water shut off that will last up to ten (8) hours. During this time, there will be no water available from the taps or toilets. Read more »

February 282019

Temporary Traffic Bridge Installation at Mount Pleasant Station

What Work is Taking Place?

As early as Monday March 4, 2019 crews will begin assembling and installing a temporary traffic bridge within the southeast corner of Mt Pleasant Road and Eglinton Avenue East. Read more »