Daytime Concrete Pours at Fairbank Station: June 19 & June 21, 2019

Looking for information related to a specific area?

Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).

 
June 18, 2019

What Work is Taking Place?

On Wednesday June 19 and Friday June 21, crews will perform concrete pours at the main entrance station box of Fairbank Station. Work will begin as early as 7:00am and the pour will be ongoing for approximately 6 hours. The concrete will form walls in the station’s main entrance. Concrete pumps will be placed at Vaughan Road and within the Main Entrance workzone. Dufferin Street and Eglinton Avenue West will remain open while work takes place. 

 

Hours of Work 

  • Wednesday June 19 and Friday June 21, 2019 beginning at 7:00 a.m. for approximately 6 hours.
  • In the event of inclement weather, this work will be rescheduled.
Construction Staging
Concrete Pour Fairbank Station
What to Expect
  • Noise and lighting from construction activity can be expected.
Traffic and Pedestrian Details
  • The pedestrian route around the southeast work zone will remain closed during this activity.
  • The pedestrian route on the east side of Dufferin will remain closed. The north, south, and west crosswalk will remain open. 
  • Access to properties along Eglinton Ave W and Dufferin St will be maintained.
  • No impacts to TTC bus service. 

Travelling Smart during Construction

  • Sign up for e-mail updates at http://www.thecrosstown.ca/sign-up or download the aCrosstown traffic app to get real-time traffic and transit information for the Eglinton corridor.
  • Travel delays are expected with construction. Please allow extra time for your journey.
  • Traffic will be extra heavy at peak periods during Eglinton Crosstown LRT construction.
  • Download the free ‘aCrosstown’ traffic app to get real-time traffic and transit information for Eglinton Avenue.

 