Decommissioning Monitoring Wells – Zone One February 24, 2020 – March 2, 2020
Looking for information related to a specific area?
Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).
- Allen Road
- Avenue Road
- Bathurst Street
- Bayview Avenue
- Bermondsey Road
- Birchmount Road
- Black Creek Drive
- Brentcliffe Road
- Caledonia Road
- Chaplin Crescent
- Don Mills Road
- Donlea Drive/Hanna Road
- Don Valley Parkway (DVP)
- Dufferin Street
- Ferrand Drive
- Ionview Road
- Keele Street
- Kennedy Road
- Laird Drive
- Leslie Street
- Lebovic Avenue
- Little Blvd.
- Mount Pleasant Road
- Oakwood Avenue
- Petman Avenue
- Pharmacy Avenue
- Victoria Park Avenue
- Warden Avenue
- Weston Road
- Wynford Drive
- Yonge Street
What Work is Taking Place?
As early as Monday February 24, 2020, crews will begin decommissioning monitoring wells across the alignment. The wells served as part of the Geotechnical Instrumentation and Monitoring Program (GIMP) during the tunneling phase of construction. Crews will be decommissioning wells as far west as Emmett Avenue and Eglinton Avenue West, and work their way as far east as Kennedy Road. The wells are divided into 10 zones. Some wells will require temporary lane reductions in the area. When a lane reduction is required, one lane will remain open, and two-way traffic will be controlled by traffic control personnel and Paid Duty Officers.
Zone One – Emmett Avenue to Black Creek Drive
Decommissioning one well will take approximately two hours. Upon completion, crews will move onto the next well, beginning at Emmett Avenue working their way east towards Black Creek Drive.
Hours of Work
- As early as Monday February 24, 2020 until as early as Monday March 2, 2020.
- Decommissioning will begin as early 9:00am until 4:00pm.
- The contractor may not always work during the permitted hours but may do so at its discretion.
- Work may be rescheduled due to weather conditions or unforeseen circumstances.
- This work may be longer or shorter than expected.
What to Expect
- Crews will be using a drill rig to decommission monitoring wells from the tunneling phase of the Eglinton Crosstown construction.
- Occasional lane reductions may be required, depending on the location of the well.
- Eglinton Ave W and adjacent streets will remain open.
- Property access will be maintained.
- Expect delays when travelling near workzones.
Work Area Map
Traffic Details
- Access to properties will be maintained.
- All current construction staging for Crosstown workzones will remain in place.
- In addition to construction activity, residents can expect to see equipment and material storage within designated work zones.
- Travel delays are expected with construction. Please allow extra time for your journey.
Travelling Smart During Construction
Travel delays are expected with Crosstown construction. Please allow extra time for your journey. Traffic will be extra heavy at peak periods during Crosstown construction. When possible, please travel during the off-peak period between 10:00 a.m. and 3:00 p.m.
Stay Informed
Sign up for email updates at www.thecrosstown.ca/sign-up or download the aCrosstown traffic app to get real-time traffic and transit information for the Eglinton Corridor.
Disponible en français
For more information about this station please contact Lancefield Morgan at the West Community Office at 416 482-8118