Geotechnical Works at the Future Cedarvale Station
Looking for information related to a specific area?
Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).
Choose an intersection (A to Z)
- Allen Road
- Avenue Road
- Bathurst Street
- Bayview Avenue
- Bermondsey Road
- Birchmount Road
- Black Creek Drive
- Brentcliffe Road
- Caledonia Road
- Chaplin Crescent
- Don Mills Road
- Donlea Drive/Hanna Road
- Don Valley Parkway (DVP)
- Dufferin Street
- Ferrand Drive
- Ionview Road
- Keele Street
- Kennedy Road
- Laird Drive
- Leslie Street
- Lebovic Avenue
- Little Blvd.
- Mount Pleasant Road
- Oakwood Avenue
- Petman Avenue
- Pharmacy Avenue
- Victoria Park Avenue
- Warden Avenue
- Weston Road
- Wynford Drive
- Yonge Street
March 24, 2016
Information as of March 24, 2016
Geotechnical Works at the Future Cedarvale Station
Upcoming Works – Geotechnical Testing
- Crews will drill three bore holes in the road asphalt to determine the condition of existing soil, rocks and utilities in the area.
- Bore holes will be drilled along the east side of Winnett Avenue south of Eglinton Avenue West.
Timing
- Geotechnical works will begin as soon as Monday, March 28, and continue for approximately four weeks
- Geotechnical works will be conducted between the hours of 9:00 a.m. and 4:00 p.m.
What to expect
- Nearby residents and businesses can expect to hear noise related to drilling, saw-cutting, and the use of heavy equipment.
Traffic Impacts
- A drill rig will occupy the curbside lane approximately 3 metres by 9 metres and a drill transport will occupy an area of approximately 3 metres by 20 metres to the south of the drill rig.
- Equipment is removed at the end of each work day.
- Pedestrian and property access will be maintained.
- As always, please take care when travelling near work sites.
Please Contact Us
For more information about the demolition work or the Crosstown LRT project, please contact Stas Ukhanov at 416-782-8118.