Geotechnical Works at the Future Cedarvale Station

Looking for information related to a specific area?

Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).

 
March 24, 2016

Information as of March 24, 2016

 

Geotechnical Works at the Future Cedarvale Station

 

Upcoming Works – Geotechnical Testing 

  • Crews will drill three bore holes in the road asphalt to determine the condition of existing soil, rocks and utilities in the area.
  • Bore holes will be drilled along the east side of Winnett Avenue south of Eglinton Avenue West.

Road works on Winnett

Timing

  • Geotechnical works will begin as soon as Monday, March 28, and continue for approximately four weeks
  • Geotechnical works will be conducted between the hours of 9:00 a.m. and 4:00 p.m.

What to expect

  • Nearby residents and businesses can expect to hear noise related to drilling, saw-cutting, and the use of heavy equipment.

Traffic Impacts

  • A drill rig will occupy the curbside lane approximately 3 metres by 9 metres and a drill transport will occupy an area of approximately 3 metres by 20 metres to the south of the drill rig. 
  • Equipment is removed at the end of each work day.
  • Pedestrian and property access will be maintained.
  • As always, please take care when travelling near work sites.

Please Contact Us

For more information about the demolition work or the Crosstown LRT project, please contact Stas Ukhanov at 416-782-8118.

 

Thank you for your continued patience as we work to build this important project.

 

Please support your local businesses during construction