August 132019

Guideway Excavation at Ionview Road

What Work is Taking Place?

As part of the ongoing LRT works at intersections along Eglinton Avenue East in support of construction of the future surface stops, crews will be conducting guideway works at the Ionview intersection at Eglinton Avenue East. Guideway construction will continue through the Ionview Road intersection as early as August 15 and be in place for approximately six (6) w Read more »

August 092019

Guideway Excavation from Rosemount Drive to Ionview Road

What Work is Taking Place?

As part of the ongoing LRT works at intersections along Eglinton Avenue East in support of construction of the future surface stops, crews will be conducting guideway works at the Ionview intersection at Eglinton Avenue East.

As early as August 12, 2019, Stage 1 will commence with the construction zone shifting to the center of Eglinton Avenue East between Rosemount Drive and Ionview Road and be in place for approximately one (1) week. Read more »

July 102019

Update: Eastbound Left Turn Reinstated at Rosemount Drive at Eglinton Avenue East

What Work is Taking Place?

As part of the ongoing works to build the LRT system along Eglinton Avenue East, crews will be replacing the existing culvert at Massey Creek. Work began as early as late February 2019 and will last for approximately nine (9) months. The creek is located at the signalized intersection of Eglinton Avenue East and Rosemount Drive. Read more »

May 312019

Construction Notice: Street Light Installation between Rosemount Drive and Ionview Road

Street Light Installations

Rosemount Drive & Ionview Road

What Work is Taking Place? Read more »

April 112019

Eastern Works Open House

Thank you for attending the Eastern Work Open House on April 10, 2019. For those of you who missed it, the presentation is here:

Download the presentation

March 212019

Sidewalk Closure for Massey Creek Culvert Work

Sidewalk Closure for Massey Creek Culvert Work

 

What Work is Taking Place?

As part of the ongoing works to build the LRT system along Eglinton Avenue East, crews will be replacing the existing culvert at Massey Creek. Work began as early as late February 2019 and will last for approximately nine (9) months. The creek is located at the signalized intersection of Eglinton Avenue East and Rosemount Drive. Read more »

March 052019

Overnight Sanitary Pipe Installation between Ionview Road and Kennedy Road

What Work is Taking Place?

In support of the construction of the future Kennedy Station, crews will be conducting sanitary pipe installation activities in the center of Eglinton Avenue East, between Ionview Road and Kennedy Road. This work is expected to begin as early as March 6, 2019 and lasting for approximately one (1) week.

In an effort to minimise disruption and to protect the safety of the local community and commuters, work will be performed overnight.

Stage 1    Read more »

February 272019

East At-Grade Town Hall Meeting

Our town halls provide information on construction impacts on Eglinton Avenue East between Credit Union Drive to Ionview Road feature detailed project maps and imagery. You can see the presentation here:

Read more »

February 252019

Overnight Invert Concrete Pours at Kennedy Station

What Work is Taking Place?

As part of continued support for the future Kennedy Station portal construction, crews will be delivering and pouring cement along Eglinton Avenue East between Ionview Road and Kennedy Road on Thursday, February 28, 2019 from 4:00 a.m. until 4:00 p.m. To facilitate this delivery, concrete trucks will be arriving to the site from the east and west Eglinton Avenue East.

Stage 1 Read more »

January 312019

Updated: Hydro Utility Relocation between Birchmount Road to Kennedy Road

What Work is Taking Place?

In support of construction of the future Crosstown Light Rail Transit, crews will continue relocation and upgrading of existing overhead and underground utilities between Birchmount Road and Kennedy Road. Work began in June of 2017 and will continue for another six (6) months. Read more »