Kennedy Road

Looking for information related to a specific area?

Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).

Syndicate content
 
November 282016

Subsurface Utility Engineering (SUE) Investigation at Kennedy Station - Updates

What Work is Taking Place?

  • Crews will continue with preparatory work for Kennedy Station by conducting Subsurface Utility Engineering (SUE) Investigation within the GO Corridor to locate existing underground utilities within the boundaries of the east corridor and future west corridor.

Timing Read more »

November 072016

Update: Geotechnical Works continue at Kennedy Station

What Work is Taking Place?

  • In February 2016, crews began conducting geotechnical works along Eglinton Avenue East to make way for the future Eglinton Crosstown LRT.
  • Pending TTC approval and City of Toronto permits, crews will drill boreholes in the roadway along Eglinton Avenue East in the vicinity of Kennedy Station, from Rosemount Drive to West of Midland Avenue to determine the condition of existing asphalt soil and rocks. 

Timing Read more »

October 262016
September 202016

Enbridge Gas Distribution Line Relocation near Kennedy Station

What Work is Taking Place? 

  • To accommodate the construction of the Eglinton Crosstown LRT, Enbridge Gas Distribution (Enbridge) is required to relocate a gas line on Eglinton Avenue East between Ionview Road and Kennedy Road. These pipelines are integral to Enbridge’s gas system and must be re-routed to ensure the safe and reliable delivery of natural gas to customers in the Greater Toronto Area.

Timing Read more »

September 062016

Pedestrian Safety near Construction Sites

Construction of the Eglinton Crosstown LRT line, including 15 underground stations, is underway. Since the end of school, many construction sites have been set up for station construction and the set-up of some major intersections along Eglinton Avenue has been changed.

Pedestrian Information Read more »

August 242016

Overnight Subsurface Utility Engineering Investigation at Kennedy Station

What Work is Taking Place?

Utility investigation work onsite within TTC land at Kennedy Station and Transway Crescent continues to determine the location and depth of existing utilities. 

Upcoming Utility Investigation

Crews will drill and hydro-vacuum overtop of existing utilities within the TTC boulevard and roadway, then a surveyor will examine the utilities to obtain coordinates for design purposes.  Read more »

August 112016

Update: Subsurface Utility Engineering (SUE) Investigation continues at Kennedy Station

 

What Work is Taking Place?

In June 2016, crews began SUE investigation in the vicinity of Kennedy Station along Eglinton Avenue East between Kennedy Road and Midland Avenue, including North Service Road, to determine the location and depth of existing utilities. 

This work continues, and similar work will begin at Transway Crescent and South Service Road. 

 

Upcoming SUE Investigation Read more »

August 022016

Clearing and Grubbing at the Future Kennedy Station

Kennedy Station will be the terminal station at the eastern end of the LRT line, and will also serve as an interchange station. It will be located at Transway Crescent and Eglinton Avenue East, approximately 300 metres east of Kennedy Road. 

What work is Taking Place?

In preparation for station construction, crews will be clearing and grubbing in the vicinity of Eglinton Avenue East and Kennedy Road for the upgrading and relocation of utilities and the widening of the Eglinton Avenue East roadway. Read more »