October 302017

Toronto Hydro-Electric System Limited (THESL) and Telecommunication Relocations (Brentcliffe to Leslie)

What Work is Taking Place?

Crews will relocate and upgrade existing overhead and underground telecommunication and hydro utilities between Brentcliffe Road and Leslie Street along Eglinton Ave East in preparation for construction of the Brentcliffe Portal and Sunnybrook Park Stop. Read more »

October 242017

Overnight Sanitary Sewer Relocation for Brentcliffe Portal

What Work is Taking Place?

Crews will relocate an existing sanitary sewer line on Eglinton Avenue East between Brentcliffe Road and Leslie Street to support the upgrade of existing infrastructure at the future Brentcliffe Portal and Sunnybrook Park Stop. 

To minimize traffic disruption for the community, transit users and local businesses, this work is being done overnight. Paid Duty Police Officers will maintain safe traffic flow. Read more »

October 202017

Installation of Temporary Traffic Signals Across Eglinton Avenue East Between Leslie Street and Kennedy Road

What Work is Taking Place?

Crews will remove existing traffic signals and install temporary traffic signals on Eglinton Avenue East between Leslie Street and Kennedy Road, to make way for the construction of future surface stops for the Eglinton Crosstown LRT.

Timing Read more »

October 162017

Early Morning Concrete Pour at Brentcliffe Portal

What Work is Taking Place?

Crews will be pouring the concrete foundation for the Brentcliffe Portal.  Work will be conducted within the existing work zone located on Eglinton Avenue East between Brentcliffe Road and Leslie Street. Due to the large size of these concrete pours, work will start at 5:00 a.m. in order to complete the pour during daytime hours, reducing impact to traffic in the area. Read more »

October 062017

Brentcliffe - Victoria Park Construction Liaison Committee Meeting

The construction liaison committee meeting of Brentcliffe - Victoria Park was held on October 5, 2017. You can see the presentation here:

Read more »

September 282017

UPDATED: Ongoing Preparatory Works between Leslie and Midland: Street Furniture Removals

Updated: September 28, 2017
Original Issue Date: May 10, 2017

What Work is Taking Place? 

As part of ongoing preparatory works, crews will begin the process of removing street furniture across the Eglinton Avenue East corridor between Leslie Street and Midland Avenue. Read more »

September 132017

Early Morning Concrete Pour at Brentcliffe Portal

What Work is Taking Place?

Crews will be pouring the concrete foundation for the Brentcliffe Portal.  Work will be conducted within the existing work zone located on Eglinton Avenue East between Brentcliffe Road and Leslie Street. Due to the large size of these concrete pours, work will start at 4:00 a.m. in order to complete the pour during daytime hours, reducing impact to traffic in the area.   Read more »

September 082017

Brentcliffe - Victoria Park Construction Liaison Committee Meeting

The construction liaison committee meeting of Brentcliffe - Victoria Park was held on September 7, 2017. You can see the presentation here:

Read more »

August 292017

Pedestrian Safety near Construction Sites

The tunnelled section between Brentcliffe Road and Black Creek Drive is complete, and last year, construction activities began at all 15 underground stations including Kennedy Station. The preparatory works at the at-grade portion of the line, between Brentcliffe Road and Kennedy Station, also started this summer. Since the end of school, many work zones have been set up for construction and some major intersections along Eglinton Avenue have changed.

Read more »

August 012017

Early Morning Concrete Pour at Brentcliffe Portal

What Work is Taking Place?

Crews will be pouring the concrete foundation for the Brentcliffe Portal.  Work will be conducted within the existing work zone located on Eglinton Avenue East between Brentcliffe Road and Leslie Street. Due to the large size of these concrete pours, work will start at 3:00 a.m. in order to complete the pour during daytime hours, reducing impact to traffic in the area.   Read more »