What Work is Taking Place? 

Crews will be working within the roadway from Guestville Avenue to Weston Road installing new hydro ductbanks. This work is anticipated to begin as early as May 1st from 7:00 a.m. and 6:00 p.m. daily.  This work is expected to last approximately 15 weeks.

workzone at Eglinton and Weston Road

Hours of Work

  • Work will occur over a 15 week period, beginning on May 1st, 2018.
  • The majority of this work will occur between the hours of 7:00 a.m. and 6:00 p.m. daily
  • Work may be rescheduled due to weather conditions or unforeseen circumstances.

 

What to Expect

  • Rolling lane closures from Guestville Avenue to Weston Road throughout the course of the work. Directional signs will be provided 
  • Turning restrictions at Eglinton Ave and Weston Road intersection will be in place for Stage 1 of this work
  • Temporary no left turn onto Guestville from Eglinton Avenue West.
  • Centre median closure at Weston Road and Eglinton Avenue West towards the end of the work schedule
  • Two (2) westbound lane closures before the Weston Road and Eglinton intersection. 

 

Pedestrian Details

  • Sidewalk access will be maintained at all times
  • During this work the east and west intersection crossings will be closed intermittently over the course of a seven (7) weeks.

 

For more information, please contact Lancefield Morgan at the West Community Office.

Thank you for your continued patience as we work to build this important project.

Please support your local businesses during construction.

 

Sign up at www.thecrosstown.ca/sign-up to receive regular email updates.