October 16 2018

Construction Notice - Mount Pleasant - Road Closure

Mount Pleasant Road Closure

Watermain Repair Update

What Work is Taking Place?

In the early hours of October 16, 2018 a watermain ruptured in the vicinity of Mt. Pleasant Road and Eglinton Avenue East. Read more »

October 15 2018

Watermain, Storm, and Sanitary Relocation at Eglinton Avenue East and Swift Drive Intersection

What Work is Taking Place?

As part of the construction of the future surface area stops, crews continue to upgrade and relocate wet utilities along Eglinton Avenue East between Credit Union Drive and Swift Drive.

In an effort to minimize disruption and to protect the safety of the local community and commuters, work will be performed overnight beginning as early as Monday, October 22nd, 2018 and last for approximately two (2) weeks. Read more »

October 15 2018

Traffic Changes at Don Mills and Eglinton for Science Centre Station

ORIGINAL POST: OCTOBER 5, 2018

Upcoming Traffic Changes at Don Mills and Eglinton

What Work is Taking Place? Read more »

October 12 2018

Update: Upcoming Traffic Changes at Kennedy and Eglinton Intersection in Support of Shoring Work

Originally Published: October 12, 2018

Updated: October 19, 2018

What Work is Taking Place?

As part of the continued support of excavation works (shoring) and utility relocations for the future Kennedy Station, traffic staging at the intersection of Kennedy Road and Eglinton Avenue East will be changing in October. Shoring began in April 2018 and will continue in phases at the intersection. Read more »

October 12 2018

Construction Notice - Additional Monitoring Wells at Avenue Station

DATE: Additional Monitoring Wells at Avenue Station

 

WHAT WORK IS TAKING PLACE?

 

Over the next two weeks, crews will work to install additional monitoring wells required for Avenue Station, east of the Secondary Entrance. The wells will be installed in the area around Eglinton Avenue W and Oriole Parkway. These wells support the ongoing monitoring instruments installations required during the construction of Avenue Station. Read more »

October 12 2018

Watermain Lining Work Avenue Station

UPDATE: WATERMAIN LINING & TEMPORARY WATER SERVICE

AVENUE STATION SECONDARY ENTRANCE

 

 

WHAT WORK IS TAKING PLACE? Read more »

October 11 2018

Eglinton Avenue West Lane Restriction For Signal Installations At Cedarvale Station

What Work Is Taking Place?

To accommodate upcoming shoring activities for the new Cedarvale LRT Station, crews will be relocating and installing new traffic poles and signal equipment along Eglinton Avenue West from Park Hill Road to Allen Road North.

Hours of Work Read more »

October 11 2018

Large Tower Crane Delivery and Installation at Kennedy Station

What Work is Taking Place?

On Tuesday, October 16, 2018 a large tower crane will be delivered to Kennedy Station in advance of deep excavation works. The tower crane will be erected at Compound 2, within the existing construction zone at Kennedy Station (adjacent to Transway Crescent). 