August 01 2018

Construction Notice - Leaside Station - Traffic Flip

UPDATE: TRAFFIC & PEDESTRIAN CHANGES

LEASIDE STATION

 

In early August, the traffic conditions at Bayview Avenue and Eglinton Avenue East will change. There will be lane reductions on Bayview Avenue as well as new turn restrictions at the intersection. Read more »

August 01 2018

UPDATE: Upcoming Traffic & Pedestrian Changes at Eglinton Station

What Work is Taking Place?

Support of excavation work, also known as shoring, has commenced to make way for the future Eglinton interchange station. This work will include pile installation, jet grouting and road deck installation. Shoring at the TTC bus depot and along south side of Eglinton has been complete. The work is carried out along the north side of Eglinton.

The next phase (depicted below) will take approximately 2-3 months to complete. The entire shoring process will take approximately twenty-four (24) months to complete. Read more »

July 26 2018

Cedarvale & Forest Hill Construction Liaison Committee Meeting

The construction liaison committee meeting of Cedarvale and Forest Hill Stations was held on July 25, 2018. You can view the presentation here:

Download the presentation

July 26 2018

Upcoming Works at Eglinton Station: Subsurface Utility Engineering (SUE) Investigations

What Work is Taking Place?

To prepare for upcoming shoring activities, crews will be conducting Subsurface Utility Engineering (SUE) investigations along the right-of-way on the south side of Eglinton Avenue from Cowbell Lane to Holly Street. Pedestrian access along Eglinton Avenue East from Cowbell Lane to Holly Street will be maintained.

Crews will drill bore holes and use a hydro-vacuum truck within the public right-of-way to determine the location of the underground utilities and the ground conditions around the intersection for design purposes.  Read more »

July 23 2018

UPDATE: Additional Monitoring Wells at Avenue Station

WHAT WORK IS TAKING PLACE?

Two additional monitoring wells are required at the Avenue Station, east of the Secondary Entrance. These wells  support the ongoing monitoring instruments installations required at Avenue Station. Read more »

July 20 2018

Upcoming Traffic Changes at Kennedy and Eglinton In Support of Shoring

What Work is Taking Place?

As part of the continued support of excavation works (shoring) and utility relocations for the future Kennedy Station, traffic staging at the intersection of Kennedy Road and Eglinton Avenue East will be changing in late July. Shoring began in April 2018 and will continue in phases at the intersection, taking approximately twelve (12) months to complete. Read more »