July 15 2020

Notice of Water Shut-off and Overnight Watermain Connection Work at Mount Pleasant Station - July 19 – 24, 2020

 

What Work is Taking Place?

Starting Sunday July 19, 2020, crews will perform overnight watermain connection work in the existing work zone on the north side of Eglinton Avenue, west of Mt. Pleasant Road.  This work will take approximately one (1) week to complete.

A water shut-off is required to facilitate this work.  The water shut-off will take place overnight on Wednesday July 22, 2020.  Please carefully review the ‘Water Shut-off Details’ section to determine whether your property will be affected. Read more »

July 15 2020

Lane Reduction for U-Fill Pour at Caledonia Station July 16, 2020

What Work is Taking Place?

On Thursday July 16, crews at Caledonia will be pouring u-fill into the station box. During the pour, westbound Eglinton Ave W will be reduced to one (1) lane only between Blackthorne Ave and Gabian Way. Lane reductions will begin as early as 5:00am and last for approximately ten hours.

Hours of Work Read more »

July 15 2020

SHELTER INSTALLATION AT WYNFORD STOP, July 15, 2020

What Work is Taking Place?
As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will install permanent shelters at the Wynford Stop north platform. Installation will begin as early as July 15, 2020 for approximately three (3) days. Lane closures will be required for this work.  Read more »

Categories:
July 15 2020

Shelter Installation at Wynford Stop North Platform - July 15, 2020

What Work is Taking Place?

As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will install permanent shelters at the Wynford Stop north platform. Installation will begin as early as July 15, 2020 for approximately three (3) days. Lane closures will be required for this work.  Read more »

July 14 2020

Lane Reduction for Concrete Pour at Caledonia Station July 15, 2020

What Work is Taking Place?

On Wednesday July 15, crews at Caledonia will be pouring concrete to form walls within the station box. During the pour, westbound Eglinton Ave W will be reduced to one (1) lane only between Blackthorne Ave and Gabian Way. Lane reductions will begin as early as 1:00pm and last for approximately four hours.

Hours of Work Read more »

July 14 2020

Trailer Installation at Chaplin Station Week of July 13, 2020

What Work Is Taking Place?

As early as the week of July 13, 2020, a new, double-stacked site trailer will be installed in the northwest corner of the Chaplin Station Main Entrance site (former Chaplin Parkette) located on the north side of Eglinton Avenue between Chaplin Crescent and Gilgorm Road.  Installation of the trailer is required to commence construction activities at the Secondary Entrance.  The trailer will remain in place into 2021.

Trailer Read more »

July 13 2020

Upcoming Concrete Pour at Oakwood Station - July 16, 2020

What Work is Taking Place?

As early as Thursday July 16, 2020, crews will perform a concrete pour within the work zone on the north side of Eglinton Avenue West at Oakwood Avenue. The concrete will form one of the permanent structures within the Main Entrance of Oakwood Station. Read more »