What's New?

Looking for information related to a specific area?

Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).

 
Syndicate content
 
August 31 2018

UPDATED: Pre-cast Concrete Installation for Facility Services Building Construction at Eglinton Station

What Work is Taking Place?

Beginning as early as September 8, 2018, crews will install pre-cast concrete for the Facility Services Building for the TTC Line 1 Subway system . Crews will also undertake various activities inside the TTC station. Read more »

August 30 2018

Watermain Lining & Valve Installations at Oakwood Station - September & October 2018

WHAT WORK IS TAKING PLACE?

To increase the durability of local watermains during mining operations at Oakwood Station, sections in the vicinity of station construction zone will be lined. Lining of the watermain is a minimally invasive method of repair and rehabilitation that is commonly used throughout the City of Toronto. Using this process allows us to complete the work without excavating the entire watermain through the road.  As part of the watermain work, a number of valves will also be installed along Eglinton Avenue between Times Road and Alameda. Read more »

August 29 2018

UPDATE: Overnight Water Outage Notice on Eglinton Avenue East - August 29-30, 2018

What Work is Taking Place?

As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will continue upgrading and relocating wet utilities in the center of Eglinton Avenue East between Victoria Park Avenue and Birchmount Road; the work commenced August 20th and will last for approximately four (4) weeks. In order to complete this stage of work a water outage is required. Read more »

Categories:
August 29 2018

UPDATE: Watermain, Storm and Sanitary Relocation at Kennedy Station Ionview Road to Kennedy Road

What Work is Taking Place?

As part of construction of the future Kennedy Station, crews continue to upgrade and relocate wet utilities along Eglinton Ave between Ionview Road and Kennedy Road.

 Crews continue to work on installing the new storm and sanitary system from Ionview to Kennedy and will complete their work with a final connection to the existing manholes located within the Kennedy and Eglinton intersection. Read more »

August 29 2018

UPDATED: Wilson Brook Culvert Work Begins East of Future Sloane Stop

What Work is Taking Place?

As part of the ongoing works to build the LRT system along Eglinton Avenue, work on the Wilson Brook Culvert will be taking place on the south and north side of Eglinton Avenue in front of 1730 Eglinton Avenue East. This work is expected to begin as early as Wednesday, August 16 to December 15, 2018.

Crews will be building a temporary storm drain line, as well as excavating and replacing the storm water culvert under Eglinton Ave East. Read more »

August 27 2018

UPDATE: Overnight Temporary Water Shutoff on Eglinton Ave E between Pharmacy and Warden - Aug 29 & Aug 30

What Work is Taking Place?

As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will continue upgrading and relocating wet utilities in the center of Eglinton Avenue East between Victoria Park Avenue and Birchmount Road; the work commenced August 20th and will last for approximately four (4) weeks. In order to complete this stage of work a water outage is required. Read more »

Categories:
August 24 2018

Construction Notice: New Street Light Installation and Civil Work on Eglinton Ave E starting August 27, 2018

What Work is Taking Place?

In support of construction of the future At Grade stops, crews will be conducting new street light installation and civil works on Eglinton Avenue East between Victoria Park Avenue and Pharmacy Avenue starting as early as Monday, August 27th, 2018 with an anticipated completion date of December 2018. Read more »

August 24 2018
August 23 2018

UPDATE: Overnight Watermain Relocation at Science Centre Station

What Work is Taking Place?

As part of the ongoing watermain upgrades for the future Science Centre Station, crews will be conducting overnight watermain relocation works at the intersection of Eglinton Avenue East and Don Mills Road.

 In an effort to minimize disruption and to protect the safety of the local community and commuters, work will be performed overnight beginning as early as Sunday August 26, 2018 and will continue for approximately five (5) nights. Read more »