November 17 2020

Laird Station Overnight Backfilling Works - November 18 2020

What Work is Taking Place?

As early as November 18, 2020, crews will begin backfilling activities at the south west corner of Eglinton and Laird Drive. Work will take place between the hours of 9:00p.m. to 5:00 a.m. Monday to Saturday for a period of two (2) weeks.

 

What to Expect

November 17 2020

Sidewalk Construction at Eglinton Ave E and Hakimi and Lebovic Ave - East Side

 

 

What Work is Taking Place?

Crews will be constructing final sidewalks at the four corners of the Eglinton Ave E and Hakimi and Lebovic Ave intersection. Work on the east side of the intersection is expected to begin November 18, 2020 for a period of one week.

What to Expect

November 16 2020

Fall Open House: Mount Dennis - Caledonia

Thank you for your interest in the Mount Dennis - Caledonia Virtual Open House on November 4, 2020. Please see the presentation below.

Read more »

November 13 2020

Science Centre Station Traffic Change at Don Mills Road and Eglinton Avenue East

What Work is Taking Place?

Crews will be performing road reconstruction works at the intersection. To accommodate these activities, a traffic change will be implemented and remain in place for approximately two weeks.

What to Expect

November 13 2020

UPDATE: Extended Hours at Laird Station

What Work is Taking Place?

Overnight working hours began at the main entrance on September 30, 2020. It has now been extended through to December 18, 2020. Permanent works at the Main Entrance will take place 24 hours a day, Monday through Friday. The current extended hours (6:00 a.m. – 1:00 a.m.) at both entrance shafts and in the tunnels, will continue through to the end of the year. Read more »

November 13 2020

Crane Footing Removals at Oakwood Station - November to Mid-December 2020

Crane Footing Removals at Oakwood Station

What Work is Taking Place?

Disassembly and removal of the overhead gantry crane is complete at Oakwood Station. Completion of this work allows crews to begin removing the gantry crane footings from the station's Main Entrance site.

November 13 2020

Concrete Pour at Laird Station - November 14, 2020

 

 

What Work is Taking Place?

Beginning November 14, 2020, crews will perform a concrete pour at the main entrance work zone at Laird Station. Preparatory work may begin as early as 6:00 a.m., the pour will take place between the hours of 7:00 a.m. and 11:00 p.m. 

 

What to Expect Read more »

November 13 2020

Sidewalk Construction at Eglinton Ave E and Warden Ave - November 16

 

What Work is Taking Place?

Crews will be constructing final sidewalks at the four corners of the Eglinton Ave E and Warden Ave intersection. Work on the west side of the intersection is expected to begin as early as November 16, 2020 for a period of one week. Work on the east side of the intersection is expected to begin as early as November 24, 2020 for a period of one week. 

November 13 2020

Lane Reductions for Sidewalk Restoration at Keelesdale Station November 9 – 20, 2020

What Work is Taking Place?

Crews at Keelesdale Station have reopened the road and completed the implementation of the final traffic configuration! Over the next few months, crews will continue with finishing activities, including final sidewalk restoration, tree planting, and street cleaning.

November 13 2020

Paving on Eglinton Avenue East at Don Mills Rd - November 17, 2020

 

 

What Work is Taking Place?

Crews will be performing paving activities on Eglinton Avenue East at Don Mills Road. To accommodate these activities, a short-term traffic change will be implemented. 

 