Mount Pleasant Road

Looking for information related to a specific area?

Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).

Syndicate content
 
August 142019

Traffic Change at Mount Pleasant Station Late August 2019

In late August 2019, a new traffic configuration will be implemented at Mount Pleasant Station. Traffic on Eglinton Avenue East will be shifted to the south side, and traffic on Mount Pleasant Road will remain on the west. The north-south crosswalk on the east side of Eglinton Avenue will remain closed, and the crosswalk on the west side of Eglinton Avenue will be open. This configuration will be in place for approximately four (4) weeks until late September 2019.  Read more »

August 092019

Extended Hours for Manhole and Sanitary work at Mount Pleasant Station August 2019

What Work is Taking Place?

Beginning Monday, August 12, 2019, crews will work extended hours install a new sewer pipe. Crews will be stationed within the existing work zone from the west edge of Taunton Rd. and Eglinton to 279 Eglinton Avenue East.  Work will be carried out between 7:00 a.m. and 2:00 a.m., Monday through Sunday for approximately three (3) weeks.  While every effort will be made to minimize disruption caused by this work, some noise and lighting can be expected. Read more »

August 082019

Overnight Traffic Change at Mount Pleasant Station

As early as August 15, 2019, a new traffic configuration will be implemented at Mount Pleasant Station. Traffic on Mount Pleasant Rd. will be shifted to the west side, and traffic on Eglinton Avenue will remain on the north. The north-south crosswalk on the east side of Eglinton Avenue will be closed, and the crosswalk on the west side of Eglinton Avenue will be reinstated. This configuration will be in place for approximately four (4) weeks until late Mid- September 2019.  Read more »

July 242019

Watermain Reinstatement Work at Mount Pleasant July 2019

What Work is Taking Place?

In late July 2019, crews will be performing watermain reinstatement work as part of the construction of Mount Pleasant Station. Work will take place within the work zones, however work in live traffic as well as overnight work may be required. A water shut-off will be required as part of the work. Affected properties will be notified separately once dates and times have been determined.

Timing Read more »

July 242019

Overnight Traffic Change at Mount Pleasant Station

In early August 2019, a new traffic configuration will be implemented at Mount Pleasant Station. Traffic on Mount Pleasant Rd. will be shifted to the west side, and traffic on Eglinton Avenue will remain on the north. The north-south crosswalk on the east side of Eglinton Avenue will be closed, and the crosswalk on the west side of Eglinton Avenue will be reinstated. This configuration will be in place for approximately four (4) weeks until late August 2019.  Read more »

July 172019

UPDATE: CROSS PASSAGE 10 AT LILLIAN STREET

Underground excavation work will commence in early August in the tunnels below Eglinton Avenue East at Lillian Street. This work will occur on a 24 hour basis with all works being completed below ground. The excavation will create a connection corridor underground between the north tunnel and the south tunnel. The work is expected to last for approximately two (2) weeks.   Read more »

June 272019

Concrete Pour at Mount Pleasant Station Friday June 28, 2019

 

On Friday June 28, 2019, crews will perform a concrete pour in the southwest work zone at Mt Pleasant Road and Eglinton Avenue.  The concrete will form part of the roof of Mount Pleasant Station.  A concrete pump will be set up within the work zone, and concrete trucks will stage on the west side of Mt Pleasant Road, north and south of Eglinton while this work takes place.  To ensure the integrity and continuity of the pour, work will begin early at 4:00 a.m. Read more »

June 172019

UPDATE: Concrete Pour at Mount Pleasant Station Wednesday, June 19, 2019

 

On Wednesday, June 19th, crews will perform a concrete pour in the southeast work zone at Mt Pleasant Road and Eglinton Avenue.  The concrete will form part of the roof of Mount Pleasant Station.  A concrete pump will be set up within the work zone, and concrete trucks will stage on the south side of Eglinton Avenue, east of Taunton Road, while this work takes place.  To ensure the integrity and continuity of the pour, work will begin early at 5:00 a.m. Read more »