Mt. Pleasant Road Closure and Overnight Work: April 27 – 30, 2018 and Overnight Water Shut-off on Friday April 27

Looking for information related to a specific area?

Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).

 
April 24, 2018

 

What Work is Taking Place?

Since April 14, crews have carried out weekend closures of Mt. Pleasant Road between Eglinton Ave E and Roehampton Ave to perform hydro utility relocation work. As part of this work, a watermain cut-and-cap will be performed, requiring a temporary water shut-off. 

To minimize the impact to affected customers as well as the number of closures required, this work will be performed overnight.  The road closure will be in place the duration of the weekend.  Through traffic on Eglinton Ave E will be maintained.

Water Shut-off Details

  • Starting:             Friday April 27 at 9:00 p.m. (overnight)
  • Duration:            Approximately nine (9) hours
  • Affected Properties:
    • 700 – 758 Mt. Pleasant Road (even numbers only)
    • 820 Mt. Pleasant Road
    • 251 Roehampton Ave
  • Note: the duration of the utility interruption may be longer or shorter than expected, and may be rescheduled due to unforeseen circumstances or inclement weather.

Upcoming Construction Staging

Hours of Work

  • Mt Pleasant Road will be closed from Friday April 27 at 9:00 p.m. until Monday April 30 at 5:00 a.m.
  • Work will be carried out on a 24-hour basis for the duration of the closure.
  • Work may be rescheduled due to unforeseen circumstances or inclement weather

What to Expect

  • Mt Pleasant Rd will be closed between Roehampton Ave and Eglinton Ave E
  • Vehicle traffic will be rerouted
  • Pedestrian and local property access will be maintained
  • Flag persons will be present to assist with traffic control

Traffic Details

  • Local access will be maintained from Roehampton Ave only.
  • Traffic lanes on Mt Pleasant Rd will be rerouted around the closure
  • Eglinton Ave E will remain open
  • TTC buses will be detoured – please look for signage

 

For more information, please contact Natalie Ardanaz at the East Community Office.

Thank you for your continued patience as we work to build this important project.

Please support your local businesses during construction.

Sign up at www.thecrosstown.ca/sign-up to receive regular email updates.