OAKWOOD STATION MINING UPDATE OCTOBER 2018

Looking for information related to a specific area?

Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).

 
October 12, 2018

 

MINING UPDATE

The Eglinton Crosstown includes a 10-kilometre underground portion, between Weston Road and Laird Drive, where 15 below-grade stations are under construction. Three stations, including Oakwood Station, are being “mined.” 

Mining operations at Oakwood Station have now been underway since early 2018. Mining occurs on a 24 hour schedule and as soon as October 15th, 2018, mining will shift to 7 days a week. Mining operations will continue to late 2019.

During mining, crews will excavate from the existing shafts at the station entrance sites and work deep beneath Eglinton Avenue. The mining technique will not be used at every location along the line but is being implemented where geology permits due to its reduced impact at street level.

Advantages of Mining 

There are many reasons for mining stations, including fewer disruptions and inconveniences for drivers, residents and businesses. While crews work below the surface, there are minimal changes to traffic, people can come and go that much easier and there is less impact on everyone’s daily lives.

Underground Activities 

The primary underground activities for safe and effective excavation include the need to ensure removal of ground water, installation of supports for the excavation, excavation and concrete works.  

As work progresses, it will occur simultaneously underground and at street level. The limited activities visible to the public will include: delivery of materials, removal of soils, equipment and pipes necessary for dewatering and ventilation. 

What You May Experience

In order to take advantage of the mining method, work will need to take place during 24-hour cycles. As a result of construction and associated truck activity, some noise and vibration may be experienced.  

Noise Reduction Measures 

Prior to this work commencing, several noise mitigation measures were explored and a noise and vibration reduction plan has been put in place. Noise barrier walls, ventilation silencers, rubber mats, alternative backup signals, enclosures for pumps and generators as well as careful sequencing of the works to minimize night time delivery and hauling have all been incorporated in order to minimize the impact that construction will have on the local community.

By expediting the construction process, this work also serves to help Metrolinx deliver better transit to the city on time.

Working Together 

Metrolinx and its contractor, Crosslinx Transit Solutions, will work together with the City of Toronto to monitor any situation of concern or disruptions. We know that during construction of this significance, residents will be inconvenienced. We will continue to work hard to keep residents informed as we deliver this important transit project. Thank you for your patience. 

STAY INFORMED

Sign up for e-mail updates at www.thecrosstown.ca/sign-up or download the aCrosstown traffic app to get real-time traffic and transit information for the Eglinton corridor.

For more information, please contact at the Lancefield Morgan West Community Office.

 

Thank you for your continued patience as we work to build this important project.

Please support your local businesses during construction.

 

Sign up at www.thecrosstown.ca/sign-up to receive regular email updates.