October 10 2019

Overnight Line Painting on Eglinton Avenue East Between Swift Drive and Sloane Avenue

Overnight Line Painting on Eglinton Avenue East Between Swift Drive and Sloane Avenue

WHAT WORK IS TAKING PLACE? Read more »

October 10 2019

Guideway Excavation at Rosemount Drive Intersection

 

What Work is Taking Place?

As part of the ongoing pavement reconstruction works at intersections along Eglinton Avenue East in support of the future surface stops, crews will be conducting guideway excavation at the Rosemount Drive intersection.  Read more »

October 09 2019

Road Widening on Eglinton Avenue east at Saddle Ridge Drive and Cranborne Avenue

Road Widening on Eglinton Avenue east at

Saddle Ridge Drive and Cranborne Avenue Read more »

October 09 2019

GUIDEWAY CONSTRUCTION ENDS AT CREDIT UNION-SWIFT

 

GUIDEWAY CONSTRUCTION ENDS AT CREDIT UNION-SWIFT   

WHAT WORK IS TAKING PLACE? Read more »

October 08 2019

Guideway Excavation from Birchmount Road to Rosemount Drive

 

What Work is Taking Place?

As part of the ongoing pavement reconstruction works along Eglinton Avenue East in support of construction of the future surface stops, crews will continue with guideway excavation from Birchmount Road to Rosemount Drive.

As early as October 9th, 2019 the construction zone will shift to the center of Eglinton Avenue East between Birchmount Road to Rosemount Drive and be in place for approximately four (4) weeks.  Read more »

October 07 2019

Update: Excavation at Chaplin Station

Excavation continues at the Chaplin Station.  Crews are excavating at the Main Entrance, located on the north side of Eglinton Avenue between Chaplin Crescent and Gilgorm Road, and at the Tertiary Entrance, located on the south side of Eglinton Avenue, east of Chaplin Crescent.Read more »

Categories:
October 04 2019

Intermittent Sidewalk Closure at Mount Pleasant Station Monday, October 7, 2019

On Monday October 7, there will be an intermittent sidewalk closure on the north side of Eglinton Ave E to complete piling work at Mount Pleasant Station. The sidewalk on the north side of Eglinton Ave E will be closed from the north-easterly corner of Mt Pleasant Rd. and Eglinton Ave to 300 Eglinton Ave E. The sidewalk closure will begin as early as  7 a.m. and take place for approximately five (5) hours. Access to the surrounding buildings and TTC will be maintained at all times. Traffic control personnel will be present while this closure takes place. Read more »

October 04 2019

GUIDEWAY CONSTRUCTION BETWEEN SLOANE AVENUE AND JONESVILLE CRESCENT

WHAT WORK IS TAKING PLACE?

Guideway construction will commence east of the future Sloane stop as early as October 14, 2019. Traffic will remain in this configuration (depicted below) for approximately six (6) months. Construction at the Wilson Brook Culvert will also continue. Crews are building a temporary storm drain line, as well as excavating and replacing the storm water culvert under Eglinton Ave East. The culvert work is located on the north side of Eglinton Avenue East between Sloane Avenue and Jonesville Crescent.

  Read more »