May 11, 2016

Since December 2015, crews have been conducting work along Eglinton Avenue West in the vicinity of the future Keelesdale Station to prepare for the next phase of construction of the Eglinton Crosstown. Work will continue through winter 2015/2016 in advance of the construction of the Keelesdale Station, which will begin in spring 2016.  

intersection of Keele and eglinton 

 

What work is starting?

Median Demolition:

·        

Demolition of four medians – two located on Eglinton Avenue West and two located at Keele Street and Trethewey Drive

·        

Work is scheduled for the hours of 7 am to 5 pm, starting as early as Monday March 7, 2016 and is expected to take approximately five days in total.

·        

The medians on Eglinton Avenue West will be removed first and then the crew will remove the medians at Keele Street and Trethewey Drive.

Watermain Replacement:

·        

Pending City of Toronto approval, activities to replace a City of Toronto watermain that runs north-south from Trethewey Drive to Keele Street will occur at night.

·        

Work is scheduled for the hours of 10 pm to 5 am, starting as early as Thursday May 12, 2016 and will last for 10 working days (14 calendar days).

·        

While every effort will be made to minimize noise, residents near the work site can expect to hear trucks, excavators, backhoes, and other construction equipment.

Pedestrian and Traffic Details:  

·        

Work to demolish the four medians will require occasional and temporary lane closures. When demolishing the medians on Keele Street at Trethewey Drive, the left turn lane from Keele Street onto Eglinton Avenue will be closed. At the end of each work day, the work zones will be plated, and traffic will return to normal function.

·        

During the replacement of the water main, one lane of traffic will be open each way on Trethewey Drive and Keele Street and one lane of traffic will be open along each way along Eglinton Avenue during work hours.

·        

A paid-duty officer will be in place to provide traffic control assistance at intersections, as required.

·        

Temporary parking and sidewalk restrictions may be in place.

·        

Access to and from properties will be maintained.

Please Contact Us

For more information, please contact Lancefield Morgan at lancefield.morgan@metrolinx.com or Tel: (416) 782-3939

 

West Community Office, 1848 Eglinton Avenue West

crosstown@metrolinx.com |www.thecrosstown.ca | 416-782-8118

 

Thank you for your continued patience as we work to build this important project.

 

Please support your local businesses during construction