April 132020

UPDATED: Shelter Installation at Westbound Pharmacy Stop - April 16-24, 2020

Original Post: March 26, 2020

Updated on April 13, 20202

 

What Work is Taking Place Read more »

April 092020

Virtual Open House: Eastern Works

The virtual open house for stations and stops between Don Mills Road and Kennedy Road was held on April 9, 2020. You can view the presentation here:


Read more »

April 012020

Pharmacy to Kennedy Construction Liaison Committee Meeting - March 2020

Construction Liaison Committee of Pharmacy to Kennedy was held on March 31, 2020. You can see the presentation here:

 

Download the presentation

March 112020

Shelter Installation at Westbound Pharmacy Stop - March 17-19, 2020

 

What Work is Taking Place

As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will install a second shelter for the westbound stop at Pharmacy Avenue and Eglinton Avenue East. The permanent shelter will be installed as early as March 17, 2020 and assembly will last for (3) days.

Work includes crane installation and shelter assembly; this will require one temporary westbound lane restriction to help facilitate work safely.

 

Work Area Map Read more »

February 282020

Stop Shelter Installation at Pharmacy Avenue and Eglinton Avenue East - March 3-6, 2020

Updated: February 28, 2020

What Work is Taking Place

As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will continue stop construction east of the Pharmacy Avenue and Eglinton Avenue East intersection. Permanent shelters will be installed as early as March 3, 2020 and assembly will last for (4) days.

Work includes crane installation and shelter assembly; this will require lane closures on either side of the mid-block guideway to help facilitate work safely.

  Read more »

January 292020

Pharmacy to Kennedy Construction Liaison Committee Meeting

The construction liaison committee meeting of Pharmacy to Kennedy was held on January 28, 2020. You can see the presentation here:

 

Download the presentation

November 272019

Pharmacy to Kennedy Construction Liaison Committee Meeting - Nov 2019

The construction liaison committee meeting of Pharmacy to Kennedy was held on November 26, 2019. You can see the presentation here:


Download the presentation

October 252019

Eastern Works Open House

Thank you for attending the Easterm Works Open House on October 24, 2019. For those of you who missed it, the presentation is here:

 

 

September 252019

Pharmacy to Kennedy Construction Liaison Committee Meeting

The construction liaison committee meeting of Pharmacy to Kennedy was held on September 24, 2019. You can see the presentation here:

 

Download the presentation

September 112019

Permanent Westbound Left Turn Lane Removal – Pharmacy Avenue

What Work is Taking Place?

In order to accommodate the future Pharmacy Stop construction, the westbound left turn lane (to southbound) will be removed at the Pharmacy Avenue and Eglinton Avenue East intersection as early as September 16, 2019.   Read more »