Pharmacy Avenue
Looking for information related to a specific area?
Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).
- Allen Road
- Avenue Road
- Bathurst Street
- Bayview Avenue
- Bermondsey Road
- Birchmount Road
- Black Creek Drive
- Brentcliffe Road
- Caledonia Road
- Chaplin Crescent
- Don Mills Road
- Donlea Drive/Hanna Road
- Don Valley Parkway (DVP)
- Dufferin Street
- Ferrand Drive
- Ionview Road
- Keele Street
- Kennedy Road
- Laird Drive
- Leslie Street
- Lebovic Avenue
- Little Blvd.
- Mount Pleasant Road
- Oakwood Avenue
- Petman Avenue
- Pharmacy Avenue
- Victoria Park Avenue
- Warden Avenue
- Weston Road
- Wynford Drive
- Yonge Street

Duct Bank Concrete Pour of Guideway from Eglinton Square to Pharmacy Avenue
What Work is Taking Place?
As part of continued support of the future surface alignment for the Eglinton Crosstown LRT, crews will conducting a concrete pour of the guideway in the center of Eglinton Avenue East between Eglinton Square and Pharmacy Avenue. Read more »
Pharmacy to Kennedy Construction Liaison Committee Meeting
The construction liaison committee meeting of Pharmacy to Kennedy was held on January 29, 2019. You can see the presentation here:
Extended: Telecommunication Relocation Work between Victoria Park Avenue and Birchmount Road
What Work is Taking Place?
As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will continue to relocate and upgrade existing overhead and underground telecommunication between Victoria Park Avenue and Birchmount Road.
Telecom work has been extended until the Spring 2019.
Duct Bank Concrete Pour of Guideway Between Eglinton Square to Pharmacy Avenue
Last Updated: January 24, 2019
What Work is Taking Place?
As part of continued support of the future surface alignment for the Eglinton Crosstown LRT, crews will conducting a concrete pour of the guideway in the center of Eglinton Avenue East between Eglinton Square and Pharmacy Avenue. Read more »
Eastern Works Open House (O’Connor Stop to Kennedy Station)
Thank you for attending the open house about Kennedy Station and O'Connor Stop to Ionview Stop on November 21, 2018. For those of you who missed it, the presentation is here:
Nightly Crosswalk Closure at Pharmacy Avenue and Eglinton to Facilitate Watermain Installation
What Work is Taking Place?
As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will be closing the east side crosswalk (north-south) at Pharmacy Avenue and Eglinton Avenue East intersection as early as Monday, November 19, 2018 for approximately four (4) nights. Read more »
Crosswalk Closure at Pharmacy Avenue and Eglinton Avenue East to Facilitate Catch Basin Installation
What Work is Taking Place?
As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will be closing the west side crosswalk (north-south) at Pharmacy Avenue and Eglinton Avenue East intersection as early as Monday, November 19, 2018 for approximately five (5) weeks.
The closure is required to provide safe and adequate space for catch basin installation and boulevard work. Read more »
Guideway Work along Surface Section of the Eglinton Crosstown LRT: Victoria Park Avenue to Pharmacy Avenue
What Work is Taking Place?
As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will be conducting guideway work in the center of Eglinton Avenue East between Victoria Park Avenue and Pharmacy Avenue starting as early as November 24, 2018 until early 2019. The work includes cutting and removal of existing asphalt, excavation, installation of subgrade materials, duct banks installation and track drainage, track slab and stops.
Stage 2: Read more »
Extended: Rolling Sidewalk Closures for Civil Road Work from Victoria Park Avenue to Pharmacy Avenue
What Work is Taking Place?
In support of construction of the future At Grade stops, crews continue civil works in relation to road widening works on both the north and south sides of Eglinton Avenue East between Victoria Park Avenue and Pharmacy Avenue. Work began in mid-September 2018.
Work has been extended until Friday, November 30, 2018. Read more »
Extended: Telecommunication Relocation Work between Victoria Park Avenue and Birchmount Road
What Work is Taking Place?
Crews will continue to relocate and upgrade existing overhead and underground telecommunication between Victoria Park Avenue and Birchmount Road, as part of construction of the future surface section for the Eglinton Crosstown LRT.
Telecom work commenced in February and has been extended until the end of the year (Fall/Winter 2018).