What's New?

Looking for information related to a specific area?

Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).

 
Syndicate content
 
August 14 2020

North and South Platform Shelter Installation at Birchmount Stop - August 24, 2020

 

What Work is Taking Place?

As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will install permanent shelters at the Birchmount Stop north and south platform. North platform installation will begin as early as August 24, 2020 for three days and the south platform will begin on August 27, 2020 for three days.  

 

What to Expect Read more »

August 14 2020

Upcoming Concrete Pour at Mount Pleasant Road and Eglinton Avenue East - Monday August 17, 2020

 

 

What Work is Taking Place?

As early as Monday August 17, 2020 crews at Mount Pleasant Station will perform a concrete pour within the work zone of the north side of Eglinton Avenue East, west of Mount Pleasant Road. The concrete will form one of the permanent station structures underground. To ensure the integrity and continuity of the pour, work will begin as early as 7:00 a.m. and take approximately five (5) hours to complete.

August 13 2020

THESL Pole Relocation - Eglinton Avenue East between Ionview and Kennedy Road - Mid-September, 2020

 

Crews will be relocating Toronto Hydro-Electric System (THESL) poles to their permanent positions along Eglinton Avenue East between Ionview Road and Kennedy Road. Work will be completed in sections and is expected to begin mid-September through to late October 2020. All works are in support of the construction of the Crosstown LRT tracks and guideway (dedicated transit lane) in the centre of Eglinton Avenue East.

  Read more »

August 12 2020

Late Night Concrete Pours at Wynford Drive and Victoria Park Avenue

What Work is Taking Place?

Starting August 2020, crews will perform late night concrete pours between Wynford Drive and the East Don River Bridge, and between Jonesville Crescent and Victoria Park Avenue. The concrete will form the plinths that will support the future tracks of the Eglinton Crosstown LRT.  Late night pours will occur twice per week, starting as early as Thursday August 13, 2020, for approximately six (6) weeks. Pours will take place between the hours of 10:00 p.m. – 3:00 a.m. Crews will endeavour to minimize disruption as much as possible. Read more »

Categories:
August 12 2020

Upcoming Concrete Pour at Oakwood Station - August 14, 2020

Upcoming Concrete Pour at Oakwood Station Aug 14 2020

What Work is Taking Place?
As early as Friday August 14, 2020, crews will perform a concrete pour within the work zone on the north side of Eglinton Avenue West at Oakwood Avenue. The concrete will form one of the permanent structures within the Main Entrance of Oakwood Station.  Read more »

August 11 2020

Concrete Pour at Eglinton Station - Thursday August 13, 2020

 

What Work Is Taking Place?

On Thursday August 13, 2020, a concrete pour will be carried out at the Eglinton Station work zone located on the southeast corner of Eglinton Avenue West and Duplex Avenue.  The concrete will form part of the station invert slab.  Concrete pumps will be setup within the work zone and concrete trucks will travel eastbound on Eglinton Avenue to Duplex Avenue to deliver concrete to the site.

 

What to Expect Read more »

August 11 2020

Concrete Pours at Mt Pleasant Road and Eglinton Avenue East - Wednesday August 12, 2020

 

As early as Wednesday August 12, 2020, crews at Mount Pleasant Station will perform concrete pours within the main and secondary entrances on the north side of Eglinton Avenue East. The concrete will form one of the permanent station structures underground. Work will begin at approximately 8:00 a.m. and is expected to take six (6) hours to complete. 

  Read more »