What's New?

Looking for information related to a specific area?

Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).

 
Syndicate content
 
December 18 2017
December 18 2017

Chaplin Station - Temporary Driveway Realignment at 564 Eglinton Avenue West

WHAT WORK IS TAKING PLACE?

Beginning December 18, crews will be performing pile installation beside the driveway of 564 Eglinton Avenue West.  To make space for the crane pad, the alignment of the driveway on Eglinton Ave W will be shifted to the west for a period of one week.  Drivers may experience delays when entering and exiting the driveway.  A flag person will be on site to assist with traffic flow.

TIMING  Read more »

December 15 2017

Overnight Traffic Set Up at Leaside Station for Stage 2

What Work is Taking Place?

On Wednesday, December 20 starting at approximately 9:00 p.m., crews will make changes to the existing traffic staging at Bayview Ave and Eglinton Ave E to accommodate the next stage of shoring in the roadway. Set up work will last approximately 14 hours. Shoring at Leaside Station is being completed in several stages. This stage 2 will be in place until approximately Spring 2018. Read more »

December 15 2017

Temporary Boulevard Occupancy for Future Micropile Load Testing for Service Building Construction at Eglinton Station

What Work is Taking Place?

In 2018, construction of an upgraded emergency ventilation system for the TTC Line 1 Subway system will get underway. The new ventilation system will be located on the TTC corridor south of Berwick used for the TTC Line 1 Subway System. Housed in a concrete structure, the new ventilation system will include smoke extraction for emergency situations at Eglinton Station. Fans will be equipped with acoustic dampers to reduce noise, and, outside of emergency situations, will only run for testing purposes. Read more »

December 08 2017

Cancelled: Overnight Sanitary Sewer Relocation for the Brentcliffe Portal Starting Friday, December 8 at 9:00 p.m.

Sanitary sewer relocation work on Eglinton Avenue East between Brentcliffe Road and Leslie Street has been cancelled due to weather. 


Updated: December 8, 2017
Previous Update Issued: November 27, 2017
Original Issue Date: October 24, 2017
Read more »

December 08 2017

Watermain Relocation between Kennedy Road and West of Midland Avenue

What Work is Taking Place?

Crews will begin the relocation and upgrading of an existing watermain on the north and south sides of Eglinton Avenue East, the North Service Road and the South Service Road from Kennedy Road to approximately west of Midland Avenue. In an effort to minimize disruption to local traffic and commuters, work will be performed in stages.   Read more »

December 08 2017

Upcoming Toronto Hydro-Electric System Development for Eglinton Station

What Work is Taking Place?

To prepare for the construction of Eglinton Station, crews have been working to re-route existing hydro utilities in the vicinity of Eglinton Avenue and Yonge Street.  Read more »