July 29 2022

Lane Reinstatement at Mt Pleasant Road and Eglinton Avenue East (As early as August 2, 2022)

What Work is Taking Place?

 As early as Tuesday, August 2, 2022, the laydown area in the center of Eglinton Avenue, between Taunton Road and Rawlinson Avenue, will be reduced. Two eastbound traffic lanes and one westbound traffic lane will be reinstated on Eglinton Avenue, east of Taunton Road. This traffic configuration will remain in place for approximately two (2) weeks. 

What to Expect Read more »

July 28 2022

Update: Sidewalk Restoration Works at Eglinton Avenue West and Oakwood Avenue - As early as July 29, 2022

What Work is Taking Place?

As early as Friday, July 29, 2022, crews will temporarily close the crosswalk on the west side of the Oakwood-Eglinton intersection for approximately 20 minutes to pave the lane. This work is expected to start at 8:00 a.m. The sidewalk on the north side of Eglinton Avenue will remain open while this work takes place.

What to Expect

July 27 2022

Update: Sidewalk Restoration Works at Eglinton Avenue West and Oakwood Avenue - As early as July 28, 2022

What Work is Taking Place?

As early as Thursday, July 28, 2022, crews will temporarily close the crosswalk on the west side of the Oakwood-Eglinton intersection for approximately two (2) hours to accommodate ongoing sidewalk restoration works. This work is expected to start at 8:00 a.m. The sidewalk on the north side of Eglinton Avenue will remain open while this work takes place.

July 26 2022

Update: Hydro Pole Installations at Avenue Station - August 2, 2022

What Work is Taking Place?

Crews at Avenue Station are currently installing hydro poles on the north side of Eglinton Avenue West. As early as Tuesday, August 2, 2022, hydro pole installations will begin on the south side of Eglinton Avenue West.

July 26 2022

Pharmacy and Kennedy CLC Presentation – July 26, 2022

Construction update for stations and stops between Pharmacy and Kennedy July 26, 2022. You can view the presentation here:

Download Presentation Here

July 25 2022

Driveway Closure at 840 Eglinton Avenue West August 8, 2022

What Work is Taking Place?

On Monday, August 8, 2022, the driveway at 840 Eglinton Avenue West will be closed at Bathurst Street to facilitate sidewalk restoration and construction works at Forest Hill Station’s Main Entrance. The closure will remain in place on a 24-hour basis, seven days a week, for approximately three (3) weeks. Affected residents have been notified directly.

July 25 2022

Notice of Water Shut-off Tuesday, July 26 – Thursday, July 28, 2022

What Work Is Taking Place?

From Tuesday, July 26 - Thursday, July 28, 2022, crews will perform watermain work at Forest Hill Station.  Nightly water shut-offs are required to facilitate the work. The water shut-offs will start at 7:30 p.m. for approximately twelve (12) hours. Water service will be restored each morning and upon completion of the work. Please carefully read the water shut-off details below.

Water Shut-off Details: