Traffic Change at Fairbank Station

Looking for information related to a specific area?

Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).

 
March 27, 2018

WHAT WORK IS TAKING PLACE?

On Wednesday, March 28, 2018, crews will implement a new traffic stage at Eglinton Avenue West and Dufferin Street for work related to support of excavation and utilities relocations, including shallow excavation at the Main Entrance, pile installation and Bell relocation in the roadway.

CONSTRUCTION STAGING

Beginning as early as March 28, 2018 for four (4) weeks.

TIMING

Permitted hours are 7:00 a.m. to 11:00 p.m., seven (7) days per week

WHAT TO EXPECT

  • Noise from construction activity as well as site lighting can be expected
  • Fencing, scaffolding, dust cloth may be erected around work zones
  • Pedestrians and road users can expect delays when travelling through the intersection

TRAFFIC AND PEDESTRIAN IMPACTS

  • Traffic lanes on Dufferin Street will shift to the east during this stage
  • The west crosswalk will close and the east crosswalk will be reinstated