December 17, 2020

 

 

What Work Is Taking Place?

TTC’s Line 1 subway will be closed between Lawrence and St. Clair stations on Saturday December 19, 2020, while crews perform structural steel installations and TTC platform relocation preparatory works.  Construction activities will include delivery of escalator trusses and installation of reinforcement steel.  Work will take place on a 24-hour basis Saturday December 19, 2020.  Berwick Avenue will remain open while this work takes place.

 

What to Expect

Noise from construction activity, including trucks.  All work zones at Yonge Street and Eglinton Avenue will remain in place.  Property access will be maintained. 

 

HOURS OF WORK

Saturday December 19, 2020

Crews will work 24 hours during the subway closure

 

TRAFFIC AND PEDESTRIAN DETAILS

No changes to the current traffic configuration and pedestrian routes are expected, as a result of this work.

 

TTC DETAILS

TTC Line 1 subway will be closed on Saturday December 19, 2020 between Lawrence and St. Clair stations.  Please visit TTC’s website www.ttc.ca, under “Service Advisories” for more information on subway closures and shuttle bus operation.

 