October 19 2017

Caledonia, Fairbank and Oakwood Stations Open House

Thank you for attending the open house about Caledonia, Fairbank and Oakwood Stations on October 18, 2017. 

For those of you who missed it, the presentation is here:

 

  Read more »

October 19 2017

Traffic Change at Fairbank Station - October 2017

What Work is Taking Place?

Since fall 2016, crews have been conducting support of excavation work (also known as shoring) at the Main Entrance and Service Building sites of the future Fairbank Station.  In the spring, crews began shoring of the station box, as well as wet utilities relocation, on the north side of Eglinton Avenue West. Read more »

October 19 2017

Traffic Change at Fairbank Station

What Work is Taking Place?

  • Since fall 2016, crews have been conducting support of excavation work (also known as shoring) at the Main Entrance and Service Building sites of the future Fairbank Station.  In the spring, crews began shoring of the station box, as well as wet utilities relocation, on the north side of Eglinton Avenue West.
  • On October 21, new temporary traffic changes will be implemented at Dufferin Street and Eglinton Avenue West, to make way for support of excavation activity as well as relocation of Bell cables at the northwest and centr
October 18 2017

Preparing to Realign Allen Road South

PREPARING TO REALIGN ALLEN ROAD SOUTH

In early 2018, the construction work zones and traffic set up will change again for the next phase of support of excavation (shoring) activities on the north side of Eglinton Avenue West at Allen Road.

This requires the Allen Road South off-ramp to be realigned approximately 20m west.

The existing All Road South off-ramp will be in place as-is until early 2018.


What Work is Taking Place? Read more »

October 18 2017

Avenue Construction Updates - October 18

Construction Activities at Avenue Road and Eglinton

As we gear up to begin mining operations at the Secondary Entrance in November, there are many other parcels of preparatory work to complete. Construction outside of the long-term set up is very active and will be for the rest of the year.

Residents and businesses can expect to see many works happening at various locations in the roadway or on the sidewalk, often at the same time.

  Read more »

October 18 2017

Traffic Reconfiguration at Don Mills and Eglinton: Overnight Work October 18 – 19, 2017

What Work is Taking Place?

As part of the continued support of excavation works for the future Science Centre station, traffic staging at the intersection of Don Mills Road and Eglinton Avenue East will be changing as early as October 18, 2017. Read more »

October 17 2017

Eglinton and Mount Pleasant Stations Open House

Thank you for attending the open house about Eglinton and Mount Pleasant Stations on October 16, 2017. 

For those of you who missed it, the presentation is here: Read more »

October 16 2017

Early Morning Concrete Pour at Brentcliffe Portal

What Work is Taking Place?

Crews will be pouring the concrete foundation for the Brentcliffe Portal.  Work will be conducted within the existing work zone located on Eglinton Avenue East between Brentcliffe Road and Leslie Street. Due to the large size of these concrete pours, work will start at 5:00 a.m. in order to complete the pour during daytime hours, reducing impact to traffic in the area. Read more »