Upcoming Traffic Change at Black Creek Drive and Eglinton Avenue West

Looking for information related to a specific area?

Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).

 
December 16, 2019

 

What Work is Taking Place?

As early as Friday December 20, 2019, the traffic configuration on Eglinton Avenue West will reopen to four lanes. All turns at Black Creek Drive and Eglinton Avenue West will be reinstated. One work zone will remain in place on the north side of Eglinton Ave W, east of Black Creek Dr until Municipal Dr.

Traffic on Black Creek Drive will remain open to four lanes. The north and east crosswalks at the intersection will remain closed. The south and west crosswalk will remain open. There will be no impacts to TTC bus service.

Hours of Work

  • The new traffic configuration will be implemented as early as Friday December 20, 2019.
  • The new traffic configuration will remain in place until as early as Summer 2020.
  • In the event of unforeseen delays, the traffic flip will be rescheduled to Saturday December 21, 2019.