July 17 2020

Upcoming Concrete Pour at Chaplin Station - Saturday, July 18, 2020

What Work is Taking Place?

On Saturday July 18, 2020, a large concrete pour will take place at the Chaplin Station Main Entrance site.  900+ cubic metres of concrete will be poured into the station box underground to form an invert slab.  The invert slab will flatten the bottom of the tunnel so that track can eventually be laid.  Two concrete pumps will be placed within work zones and several concrete trucks will deliver concrete to the site every hour.  The pour will take approximately 14 hours to complete.

  Read more »

July 16 2020

Laneway & Parking Lot Closure at Keelesdale Station

What Work Is Taking Place?

As early as Monday July 20, 2020, installation of a new storm line at Keelesdale Station will begin. This work will require closing the parking lot south of Eglinton Avenue West, west of Yarrow Road, and the laneway, east of Yarrow Road. The laneway and parking lot will be closed to all vehicular traffic, including resident vehicles, for approximately five days while this work takes place. Pedestrian access to properties via Eglinton Avenue West will be maintained.  Read more »

July 16 2020

Notice of Extension: Closure of Chaplin Cres Road Closure for Traffic Bridge Removal Works June 8 – July 31, 2020

 What Work is Taking Place?

Please note that the closure of Chaplin Crescent between Eglinton Avenue and Russell Hill Road has been extended by two (2) weeks until July 31, 2020, while crews complete traffic bridge removal, utilities reinstatement, back-filling and paving at the intersection.  The Chaplin-Russell Hill laneway closure is also extended to July 31, 2020. Read more »

July 16 2020

SHELTER INSTALLATION AT WYNFORD STOP July 20, 2020

 

Hours of Work
• Shelter installation will begin as early as July 20, 2020 for approximately one week.
• Work may be performed between the hours of 7:00 a.m. and 11:00 p.m.
• Work may be rescheduled due to weather conditions or unforeseen circumstances.

Work Area Map
  Read more »

Categories:
July 15 2020

SHELTER INSTALLATION AT WYNFORD STOP, July 15, 2020

What Work is Taking Place?
As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will install permanent shelters at the Wynford Stop north platform. Installation will begin as early as July 15, 2020 for approximately three (3) days. Lane closures will be required for this work.  Read more »

Categories:
July 15 2020

Shelter Installation at Wynford Stop North Platform - July 15, 2020

What Work is Taking Place?

As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will install permanent shelters at the Wynford Stop north platform. Installation will begin as early as July 15, 2020 for approximately three (3) days. Lane closures will be required for this work.  Read more »

July 15 2020

Notice of Water Shut-off and Overnight Watermain Connection Work at Mount Pleasant Station - July 19 – 24, 2020

 

What Work is Taking Place?

Starting Sunday July 19, 2020, crews will perform overnight watermain connection work in the existing work zone on the north side of Eglinton Avenue, west of Mt. Pleasant Road.  This work will take approximately one (1) week to complete.

A water shut-off is required to facilitate this work.  The water shut-off will take place overnight on Wednesday July 22, 2020.  Please carefully review the ‘Water Shut-off Details’ section to determine whether your property will be affected. Read more »

July 15 2020

Lane Reduction for U-Fill Pour at Caledonia Station July 16, 2020

What Work is Taking Place?

On Thursday July 16, crews at Caledonia will be pouring u-fill into the station box. During the pour, westbound Eglinton Ave W will be reduced to one (1) lane only between Blackthorne Ave and Gabian Way. Lane reductions will begin as early as 5:00am and last for approximately ten hours.

Hours of Work Read more »