August 26 2020

Boulevard Restoration Works Eglinton Ave East North Side, Ionview Road to Kennedy Road - Extended to Late September

 

Original Post: July 28, 2020

Last Update: August 26, 2020

 

What Work is Taking Place?

Crews will continue boulevard restoration works on the north side of Eglinton Avenue East between Ionview and Kennedy Road. Partial or full driveway closures will be required to perform grading works to align driveways with the new road surface on Eglinton Avenue East.  Driveways may be restricted partially or fully beginning July 6, 2020. This work has been extended through to late September 2020.  Read more »

August 26 2020

Lane Reduction for Site Maintenance at Caledonia Station August 27, 2020

WHAT WORK IS TAKING PLACE?

On Thursday August 27, crews at Caledonia will be using a vac-truck to clean the site's sediment tank. During this activity, westbound Eglinton Ave W will be reduced to one (1) lane only between Blackthorne Ave and Gabian Way. Lane reductions will begin as early as 7:00am and last for approximately four hours.

August 25 2020

Concrete Pour at Fairbank Station - August 27, 2020

Concrete Pour at Fairbank Station Aug 27

What Work is Taking Place?

Crews at Fairbank continue to perform large concrete pours. On Thursday August 27, crews will be pouring the last structural wall, from track to concourse level!

August 24 2020

Weekend Piling Activities at Kennedy Station - August 29-30, 2020

On August 29 and 30, 2020, crews at Kennedy Station will drilling four (4) piles at the decommissioned GO track at Kennedy Station. Crews will be drilling, hauling and performing concrete works. Work will take place between the hours of 6:00 a.m. and 6:00 p.m. on both days. 

Due to the nature of this work, noise and vibration can be expected at the work site. Site-based mitigation will be in place and crews will endeavor to schedule less noisy activities throughout the early morning hours. 

  Read more »

August 21 2020

Crane on Vaughan Road at Fairbank Station - August 21, 2020

What Work is Taking Place?

Crews at Fairbank station continue to use the crane installed on Vaughan Road adjacent to the Main Entrance site. Over the weekend, beginning on Friday August 21, the crane will remain in place to assist with lifting and hoisting activities. Following this weekend, crane activities will continue to take place Monday to Friday.

 

August 19 2020

Lane Reduction for Concrete Pour at Caledonia Station - August 20, 2020

What Work is Taking Place?

On Thursday August 20, crews at Caledonia will be pouring concrete to form a wall connecting to the stations roof. During the pour, westbound Eglinton Ave W will be reduced to one (1) lane only between Blackthorne Ave and Gabian Way. Lane reductions will begin as early as 6:30am and last for approximately nine hours.

 

What to Expect

August 19 2020

Closure on Rosemount Drive North of Eglinton Avenue East - Extended to late October 2020

 

As part of the ongoing works to replace the existing culvert at Massey Creek, the current traffic configuration at Rosemount Drive and Eglinton Avenue East will be extended to late October 2020. Rosemount Drive will remain closed north of Eglinton Avenue East and north-south through-traffic will be prohibited for the duration of the work. Read more »