August 06 2020

Sidewalk and Lane Closure at Laird Station Friday August 7, 2020

What Work Is Taking Place?
On Friday August 7, 2020, crews will perform a concrete pour at the Laird Station Main Entrance site.  The work will be performed using a mobile crane and several concrete trucks.  The eastbound curb lane on Eglinton Avenue East, the south sidewalk in front of Laird Station Main Entrance as well as the west and south crosswalks at Laird Drive and Eglinton Avenue East will be closed while this work takes place.  Upon completion of the pour, the lane, sidewalk and crosswalks will re-open. Read more »

Categories:
August 04 2020

REVISED: North Service Parking Lot Expansion at Kennedy Station

 

Original Post: July 31, 2020

Updated on August 4, 2020

 

What Work is Taking Place?

Crews will be expanding the TTC North Service Parking Lot north of Eglinton Avenue East at Kennedy Station. This work will take place through to late August 2020. Work may take place between 6:00 a.m. and 5:00 p.m., Monday to Friday.

 

What to Expect Read more »

July 31 2020

Antenna Installation at the Eglinton Maintenance and Storage Facility - August 6-8, 2020

 

 

What Work is Taking Place?

The Eglinton Crosstown requires a radio system to allow communication among Operator and Maintenance personnel, including dispatchers, mobile staff, and Revenue Vehicle drivers. The system requires four radio sites to ensure we have proper radio coverage along the whole alignment.

July 31 2020

UpdateOvernight Decking Reinstatement Work at Leaside Station July 27, 2020 – August 8, 2020.

What Work is Taking Place?
From Tuesday August 4 – Saturday August 8, 2020 crews at Leaside Station will work overnight to reinstate the road decking at Eglinton Avenue East and Bayview Avenue. Work will be performed throughout all areas of the intersection, with crews occupying one lane on Eglinton Avenue East and Bayview Avenue, during each night of work.

Read more »

Categories:
July 30 2020

Upcoming Concrete Pour at Oakwood Station - July 31, 2020

Upcoming Concrete Pour at Oakwood Station July 31 2020

What Work is Taking Place?

As early as Friday July 31, 2020, crews will perform a concrete pour within the work zone on the north side of Eglinton Avenue West at Oakwood Avenue. The concrete will form one of the permanent structures within the Main Entrance of Oakwood Station.  Read more »

July 30 2020

Cedarvale & Forest Hill Construction Update - July 29, 2020

The following construction update for Cedarvale and Forest Hill stations has been updated as recently as May 27, 2020. You can view the presentation here:

July 29 2020

Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2020

Construction Liaison Committee of Pharmacy to Kennedy was held on July 28, 2020. You can see the presentation here:

 

Download the presentation