July 24 2019

Overnight Traffic Change at Mount Pleasant Station

In early August 2019, a new traffic configuration will be implemented at Mount Pleasant Station. Traffic on Mount Pleasant Rd. will be shifted to the west side, and traffic on Eglinton Avenue will remain on the north. The north-south crosswalk on the east side of Eglinton Avenue will be closed, and the crosswalk on the west side of Eglinton Avenue will be reinstated. This configuration will be in place for approximately four (4) weeks until late August 2019.  Read more »

July 24 2019

Early Morning Start - Concrete Pour at Avenue Station

What Work is Taking Place?

On Tuesday July 30th, 2019, crews will perform a continuous concrete pour at Avenue Station’s secondary entrance site. The work will begin as early as 3 a.m. and will be ongoing for approximately 16 hours. The concrete will form parts of the permanent station structure underground. Read more »

July 24 2019

UTILITIES CROSSING AT BERMONDSEY ROAD AND SLOANE AVENUE AT EGLINTON AVENUE EAST

 

UTILITIES CROSSING AT BERMONDSEY ROAD AND SLOANE AVENUE AT

EGLINTON AVENUE EAST Read more »

July 23 2019

UPDATE: Construction for TPSS (Traction Power Substation) 10 Begins at Victoria Park

Original Notice posted on July 10, 2019

CONSTRUCTION BEGINS AT TPSS 10 (Traction Power Substation)

What Work is Taking Place? Read more »

July 19 2019

Concrete Pour at Fairbank Station - July 22, 2019

What Work is Taking Place?

On Monday, July 22nd, crews will perform concrete pours at the main entrance station box of Fairbank Station. Work will begin as early as 7:00am and the pour will be ongoing for approximately 10 hours. The concrete will form walls in the station’s main entrance. Concrete pumps will be placed at Vaughan Road and within the Main Entrance work zone. Dufferin Street and Eglinton Avenue West will remain open while work takes place.

Hours of Work Read more »

July 18 2019

UPDATED DATES: Weekend Traffic Restrictions at Warden Avenue

Originally Posted: July 12, 2019 

Updated: July 18, 2019

What Work is Taking Place? Read more »

July 17 2019

UPDATE: CROSS PASSAGE 10 AT LILLIAN STREET

Underground excavation work will commence in early August in the tunnels below Eglinton Avenue East at Lillian Street. This work will occur on a 24 hour basis with all works being completed below ground. The excavation will create a connection corridor underground between the north tunnel and the south tunnel. The work is expected to last for approximately two (2) weeks.   Read more »