February 25 2020

POSTPONED: Upcoming Concrete Pours with Lane Reduction at Avenue Station Thursday February 27, 2020

**This work did not occur on February 27, 2020. This work has been postponed.**

What Work is Taking Place? Read more »

February 25 2020

Tower Crane Removal at Science Centre Station

Tower Crane Removal at Science Centre Station

 

WHAT WORK IS TAKING PLACE?  Read more »

February 24 2020

Closure on Rosemount Drive North of Eglinton Avenue East - Extended Until April 1, 2020

 

What Work is Taking Place

As part of the ongoing works to replace the existing culvert at Massey Creek, the current traffic configuration at Rosemount Drive and Eglinton Avenue East will be extended until April 1, 2020. Rosemount Drive will remain closed north of Eglinton Avenue East and north-south through traffic will be prohibited for the duration of the work.

Work continues at the east wing-wall of the creek and includes excavation, concrete works, removal of form work and backfilling.  Read more »

February 21 2020

Update: Concrete Pour at Oakwood Station Monday, February 24, 2020

What Work is Taking Place? 

On Monday, February 24, 2020, crews will perform a concrete pour within the work zone on the northside of Eglinton Avenue West at Oakwood Avenue. The concrete will form one of the permanent structures of Oakwood Station. To safely carry out the works, Eglinton Avenue West will be reduced to one lane in each direction, while the pour takes place. The pour will begin at 6:00 a.m. and take approximately sixteen (16) hours to complete.   Read more »

February 20 2020
February 20 2020

Tower Crane Installation at Kennedy Station - March 14, 2020

 

What Work is Taking Place

As part of the ongoing construction of the Eglinton LRT crews will be delivering and assembling a second Tower Crane in the existing work zone at Kennedy Station. The work will take place on March 14, 2020 and last for one (1) day. 

Tractor trailers will enter from Eglinton Avenue East, through the Temporary Service Road to deliver the crane to the existing construction zone located north of Temporary Service Road and east of Transway Crescent. Read more »