Utility Relocation

Looking for information related to a specific area?

Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).

Syndicate content
 
November 202018

UPDATED: Continuation of Overnight Utilities Work at Forest Hill Station through December 2018

Originally Published: November 7, 2018 
Updated: November 20, 2018 

 

What Work is Taking Place?

Crews have been completing overnight wet utility and hydro utility installation work at Forest Hill Station since September 2018.  This work will continue through December 30, 2018.  By the end of 2018, 95% of all utilities relocation and installation work will have been completed at Forest Hill Station.

September 192018

Upcoming Toronto Hydro Relocation Work At Cedarvale Station

What Work is Taking Place? 

To accommodate upcoming shoring activities for the new Cedarvale LRT Station, crews will be relocating Toronto hydro infrastructure in the area of Everden Road and Eglinton Avenue West. For pedestrians travelling north on Everden Rd the ONLY access to Eglinton Avenue West will be through Ben Nobleman Park. Pedestrians will be routed through the pre-existing paved pathway through Ben Noblemen Park to the sidewalk on Eglinton Avenue West. Read more »

August 292018

UPDATE: Overnight Water Outage Notice on Eglinton Avenue East - August 29-30, 2018

What Work is Taking Place?

As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will continue upgrading and relocating wet utilities in the center of Eglinton Avenue East between Victoria Park Avenue and Birchmount Road; the work commenced August 20th and will last for approximately four (4) weeks. In order to complete this stage of work a water outage is required. Read more »

Categories:
August 272018

UPDATE: Overnight Temporary Water Shutoff on Eglinton Ave E between Pharmacy and Warden - Aug 29 & Aug 30

What Work is Taking Place?

As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will continue upgrading and relocating wet utilities in the center of Eglinton Avenue East between Victoria Park Avenue and Birchmount Road; the work commenced August 20th and will last for approximately four (4) weeks. In order to complete this stage of work a water outage is required. Read more »

Categories:
April 072018

Overnight Utility Relocation on Transway Crescent and Kennedy Road in Support of Construction of the Future Kennedy Station

What Work is Taking Place?

As part of construction of the future Kennedy Station, crews will be relocating watermain and sanitary utilities on Transway Crescent, including a partial crossing of Kennedy Road, starting as soon as April 9, 2018. To reduce impacts to the community and commuters this work will be performed overnight and will take approximately two weeks to complete.  The work is part of the larger upgrade and relocation of utilities for the Eglinton Crosstown LRT. Read more »

November 012017

Changes to the Driveways at 2360 Eglinton Avenue East: Stage 1

In Support of Upgrades to Water Infrastructure for the Eastern End of the Eglinton Crosstown LRT Line

Beginning as early as Monday, November 6, 2017 for approximately four (4) weeks, driveways at 2360 Eglinton Avenue East will be modified to support construction of the Crosstown LRT. Work will be done in two stages, each stage lasting approximately two (2) weeks.

Please see image below showing changes to access to 2360 Eglinton Avenue East during Stage 1 of this work.

What Work is Taking Place? Read more »

October 272017

Overnight Watermain and Sanitary Installation at Kennedy Station

Originally Issued: October 27, 2017

Updated and Reissued: November 1, 2017

What Work is Taking Place? Read more »

September 202017

Preliminary Notice to Businesses and Residents: Upcoming Power Outage Between Birchmount and Kennedy

What Work is Taking Place?

Since June 2017, crews have been upgrading and relocating existing hydro utilities in the area located just west of Birchmount Road to Kennedy Road in the vicinity of Eglinton Avenue East. To complete this work, a Hydro outage is required.

Hours of Work Read more »

March 312017

LOW WATER PRESSURE NOTICE: Watermain Investigation Work

What Work is Taking Place?

On April 3, 2017, crews will begin subsurface utility engineering (SUE) investigation of a large 900mm watermain in the Eglinton Avenue West and Chaplin Crescent area.  The watermain will be exposed to determine the utility and ground conditions in advance of wet utilities relocation.  Most of the work will take place within the existing traffic staging at Chaplin Crescent and Eglinton Avenue West. Read more »