October 12, 2018

What Work is Talking Place?

To increase the durability of local watermains during mining operations at Oakwood Station, sections in the vicinity of station construction zone will be lined. Lining of the watermain is a minimally invasive method of repair and rehabilitation that is commonly used throughout the City of Toronto. Using this process allows us to complete the work without excavating the entire watermain through the road. 

What to Expect    

Watermain lining begins - October 15

  • Starting Oct 15st - All properties switched over to the temporary water service *properties connected to the temporary water service may experience reduced water pressure.
  • Starting Oct 15st - Closure of Times Road from lane way to Eglinton Avenue.
  • Lane way access is maintained
  • Parking on Times Road between Livingston and Eglinton will be unavailable.
  • Lane reductions and on-street parking impacted periodically on Eglinton Ave W, between Oakwood and Alameda

Watermain lining work underway, October 15th to 30th, 8 p.m. to 6 a.m.  

  • Eglinton Avenue W reduced to one lane only during working hours. Two-way traffic will be facilitated with traffic control personnel.
  • On-street parking will be impacted in the area between Glenholme and Oakwood between 8 p.m. and 6 a.m.

Removal of above ground temporary water service pipes and area restoration, November 5th to November 20th, 8 p.m. to 6 a.m.  

  • Eglinton Avenue W reduced to one lane only during working hours. Two-way traffic will be facilitated with traffic control personnel.
  • On-street parking will be impacted in the area between Glenholme and Oakwood between 8 p.m. and 6 a.m.
  • TTC southbound and northbound stops will be relocated further south on Oakwood during restorations on Oakwood and Reggae Lane.

·     Residents and businesses near the work zone can expected to hear noise from generators, compressors, hydro-vacuum trucks, and other construction equipment.  

Oakwood Watermain Oct-Nov 2018 workzone

Timing

  • Work will occur between September 5th and late November 2018.
  • Work will occur between 8:00 p.m. and 6:00 a.m.
  • Overnight works are planned to reduce disruptions to traffic and transit as well as for utility outages to reduce impacts to local residents and businesses. 

 

For more information, please contact at the Lancefield Morgan West Community Office.

Thank you for your continued patience as we work to build this important project.

Please support your local businesses during construction.

Sign up at www.thecrosstown.ca/sign-up to receive regular email updates.