Yonge Street
Looking for information related to a specific area?
Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).
- Allen Road
- Avenue Road
- Bathurst Street
- Bayview Avenue
- Bermondsey Road
- Birchmount Road
- Black Creek Drive
- Brentcliffe Road
- Caledonia Road
- Chaplin Crescent
- Don Mills Road
- Donlea Drive/Hanna Road
- Don Valley Parkway (DVP)
- Dufferin Street
- Ferrand Drive
- Ionview Road
- Keele Street
- Kennedy Road
- Laird Drive
- Leslie Street
- Lebovic Avenue
- Little Blvd.
- Mount Pleasant Road
- Oakwood Avenue
- Petman Avenue
- Pharmacy Avenue
- Victoria Park Avenue
- Warden Avenue
- Weston Road
- Wynford Drive
- Yonge Street

Upcoming Works at Eglinton Station: Utilities Relocations – Stage 4
What Work is Taking Place Read more »
Update: Upcoming Works at Eglinton Station: Support of Excavation
What Work is Happening? Read more »
Upcoming Works at Eglinton Station: Utilities Relocations – Stage 3
What Work is Taking Place
Work to replace and relocate existing utilities continues to make way for the future Eglinton interchange station. Storm and sanitary sewers, water mains, hydro ducts, and telecommunications utilities are being replaced and relocated in a series of stages. During this third stage, work will take place on the south side of Eglinton Avenue, east and west of Yonge Street. Read more »
UPDATE: Demolishing the Abandoned TTC Bus Depot
What Work is Happening?
- The abandoned TTC Bus Depot (pictured below) is being demolished to make way for the new Eglinton LRT Station’s primary entrance (pictured at bottom) and new developments at Yonge and Eglinton.
Progress to Date
Utilities Relocations at Eglinton Station: Stage 2
What work is Taking Place? Read more »
Subsurface Utility Engineering at Eglinton Station
What Work is Taking Place? Read more »
Overnight Lane Reduction on Eglinton Avenue East for Crane Transport
What Work is Taking Place?
Crews will be transporting a crane into the extraction shaft construction zone area, on the north side of Eglinton Avenue East, east of Yonge Street.
Timing Read more »
Overnight Tunnel Boring Machine Removals Eglinton Avenue Closure: Yonge St. to Dunfield Ave. Nightly, April 4-7 & April 10, 2017
What Work is Taking Place?
Tunnelling is complete, and crews will be removing the south TBM, Humber, over several days in April, 2017 (April 4, 5, 7 and 10). As with Don, Humber will be disassembled and removed in pieces. The pieces will be loaded onto trucks by large cranes and transported offsite. Read more »
Eglinton Station Open House
Thank you for attending our Eglinton Station Open House on March 22, 2017.
For those of you who missed it, the presentation is here: